Rx207
Progress Report February 2013
The Mechanical Services Manager has provided the following overview of what work is being carried out on this loco following its withdrawal from operational service after the Christmas 2012 - New Year Cockle Train running which it shared with loco 621
"Rx207 has been returned to Mt Barker for assessment as to its condition and appropriate remedial action and hopefully will be back on the tracks in October / November 2013.
The Boiler is being removed for repairs to rivets around the foundation ring at the base of the firebox due to age wastage. Also there is some boiler plate of the inner firebox throat plate / front plate that has some thin spots that have began to show cracks thus requiring some sections to be replaced.
The worn driving wheel axle bearings that were not renewed during the re-tyre job are to be cast and renewed whilst the boiler is off the frame. The axle journals will have some slight taper machined out and the new bronze bearings will be cast and then machined to suit.
Time and a shortage of funds did not permit this task previously and the loco was returned to service expecting that within 3 years the boiler may have to come off for some of the current work so the bearings would hopefully last that long. The chance was taken and it turned out that the thinning plate caught up first."
Future work in 2013 will involve new baffles in the tender water space and work around the boiler foundation ring.
At the moment it appears 207's 2in. diameter dump grate support shaft has again bent from the affects of heat and the use of the ash wetter causing the dump grate to drop thereby exposing the foundation ring rivet heads to the fire. This is a "no no" because the rivets do not have water behind them to take away the heat and prevent them from being burnt.
207's droopy dump grate was fairly easily fixed. the support links were lenthened by a
bit over an inch However while ferreting around underneath we noticed a
very wet spot in the RH corner of the inner firebox.
Cleaning and drying the spot soon revealed a 1/2"
long horizontal crack in the boiler plate coinciding with the top of the foundation ring on the other side
of the plate where, traditionally, grooving occurs in the plate on the water side so the leak is no real surprise.
Such cracks automatically fail the loco so decisions have to be made with the Boiler Inspector as to whether
the crack can be effectively temporarily fixed or that part of the boiler has passed its use by date considering
the other issues including 5 wasted and leaky rivet heads. The Boiler Inspector requires the boiler to be removed from the frame after April 2013 for a complete inspection.
The frame also will be lifted from wheels for axle-box / wheels inspection.
These photos taken by Peter Michalak at Mt Barker Depot in April 2013 show Rx207 preparing for a boiler lift
And a Boiler Lift - May 14th - a report from Ian Johnston
A few photos are included below showing 207’s boiler finally being lifted from its frame
Because of the roof height restrictions the boiler could not be lifted cleanly out of 207’s frame so it was lifted part way so as to clear the top of the frame then the frame moved rearwards so as the boiler became completely clear and could be moved back towards the two cranes used. Since the cranes were then occupying the spot designated for the boiler, the boiler was temporarily left on the ground while the front and rear boiler supports were put in place. The two cranes were repositioned so that the boiler could be slewed and carefully placed on the supports.
A temporary sleeper sty has been placed under the outer throatplate as a precaution but as this is the spot where most of the repair work is required, a more permanent sty will be erected under the centre of the boiler.
Interesting in the centre photo , where the boiler is about to land on its supports, markings on the side of the firebox from 2000 for “this way up” and “keep dry” are still there!! Also to the rear of the firebox in the top 3 rows of stays can be seen a festering patch from leaky stay cups so it has been a timely exercise to find them. The third photo shows what a mess steam locos can be underneath with one highlight being the grotty looking ashpan and the perennial “whoof” in the dump grate shaft being easy to spot.
Those assisting in this work were Butch Cassidy, Daryl Simon, Trevor Sasche, Rod Stone and Nev. Pauley so many thanks to them.
And some more news - late July 2013 - a further report from Ian Johnston
It has been a while since we separated 207’s boiler from the engine and work has steadily progressed as resources permit keeping in mind there is always plenty to do in just keeping the operational trains on the move.
The plan with the boiler has been to progressively investigate all known and possible additional problem areas. This initially involved taking over 260 thickness measurements of boiler plates, principally of the lower sections of the inner firebox (both side sheets and tubeplate) and the outer plates (both wrapper and throat plates). Measurements were taken on the front half of the firebox where the known problem areas were but then also extended both towards the rear of the boiler and upwards from the foundation ring until acceptable plate thicknesses were consistently found. The measurements revealed the usual issues with locomotive boilers in that there was lots of plate wastage between the foundation ring rivet heads and in the plates for up to 150 mm above the ring. Under guidance from Boiler Inspector, Bernie Dickinson, small sections of suspect plate were progressively cut out for further visual inspections to eventually determine the full scope of the work. This work also included the removal of several flexible and rigid stays and many rivets around the foundation ring.
The main issues highlighted have included;
- the condition of all plates on the water side was quite good indicating that our water treatment regimes are keeping corrosion to a minimum.
- wastage of the inner firebox side sheets between the ring rivets due mainly to ashes trapped between the sheets and the firegrate carriers.
- both front corners of the inner firebox were cracked on the water side due to the prolonged thermal shocks over the years.
- wastage of the outer wrapper and throatplates between the ring rivet heads, this time due to outside sources of water like rain, boiler washouts, blowdowns etc.
- most of the rivets around the front half of the ring had suffered excess corrosion resulting in their heads not being as effective as desired.
- The foundation ring is in good condition even though it is original from when this boiler was built in 1932.
The photos attached show the very first section cut from the outer throatplate for the first inspection and evaluation (first photo) with subsequent shots depicting where we are currently at. A meeting with our inspector will determine if we have reached the full scope of work required. The foundation ring is in good condition even though it is original from when this boiler was built in 1932.
RH Wrapper plate ----------- Inner Firebox ------------ LH corner Wrapper plate
All photos: Ian Johnston
Late September 2010
Which follows on from a report in late September from Mechanical Services Manager, Craig Dunstan
At last so much of the hard work that has been put in by all involved over
the past 3 1/2 years is now starting to take shape. With the recent
introduction of a full time fitter back into the MB workshop and being
complimented by dedicated volunteers, has seen Rx207 move ahead again in
leaps and bounds with work concentrating on Rx207 5 - 6 days per week.
As can be seen in these photos the engine's pony truck has been reassembled
on road 4 then to be repositioned back under the engine. Many
modifications have been made by introducing grease lubrication to all of the
pony truck moving components that previously just relied upon the hope that
components received a "hopeful" drip of oil from somewhere, that generally
got sucked up by some dirt or dust and never generally made it into its
intended place. If so it did not remain there for very long which was
apparent by the many worn pins, bushes and shafts. Likewise the existing oil
lubricated bogie centre will be converted to grease lubrication with some
minor modifications to suit.
The tender wheels were finally reunited with the bogie frames
after complete rebuilding of the tender axles box bearings (they
roll beautifully with ease) and replacement of two axle boxes due to
considerable cracking of the box lower halves or oil pans. Two suitable
boxes were obtained from 207's original bogies and machined to suit.
Suitable replacement boxes will need to be sourced when rebuilding the
bogies for Rx224.
Again like the pony truck, the tender spring links have been re-bushed with
a complete new set of spring link pins being manufactured with the
inclusion of grease lubrication thus doing away with the existing oil
system. Upon disassembly all spring link pins and bushes exhibited
considerable wear requiring replacement. The tender bogie centres have also
received some minor reworking to accept grease lubrication as opposed to the
forever blocking oil system.
Further work will see the completion of bogie painting and fitting of axle
horn binders etc, with the bogies set then to be placed back under the tender.
Work will then progress to the setting out of the engine axle boxes to
install a dust shield system and beginning to reassembling the axle boxes, springs
and coupling rods onto the driving axles.
The engines blow down valve is currently undergoing overhaul to the valve
and seat with the introduction of o'ring sealing to the shaft and end cap in
attempts to eliminate the unwanted water spraying back across the boiler
throat plate and ash pan damper areas. New blow down valve studs have been
manufactured and installed in the throat plate.
Late October 2010
In late October Ian Johnston reported
Recent work on 207 has included removing both front pony mudguards and main cylinder covers. Both piston rods were disconnected from their crossheads and rod packing assemblies removed followed by the pistons - fair bit of carbon around as. Butch has started setting up the gizmos to hold and locate the piano wires through the cylinders to the rear of the frame.
Our best air jack was used to lift the loco at roughly its centre point separately on each side to encourage the main frame to spring upwards a little to refit the hornblock binders. Bit amazing to watch the binder lugs move closer together as the jack did its business so all binders are temporarily refitted as they are required to be for the frame measuring work.The loco has been levelled front and back longitudinally and laterally using laser levels - marvellous little gadgets that tell you instantly and exactly how things are sitting in the world.
Caliper and laser measuring has confirmed the pony trunnion is around 5 mm to the right of the centre of the loco using both sides of the frame as datum points. This in itself could be part or all of the reason why 207 is not right, however no-one is jumping to conclusions on that until a lot more measurements have been confirmed against the piano wires.
As another project our fitter Butch has completed machining and welding a new tender brake cylinder piston (photos right), the existing one having been written off by our inspector as being well past its effective use by date due to being old cast iron and difficult to successfully repair its cracks by brazing.
Late December 2010
One of our major milestones was accomplished on the 3rd December with 207 landing back on its wheels and on track. All the realignment work seems to have been in the right direction as everything fitted together very nicely without any real hassles. However there was still a lot work required to get the engine back over the centre of the track and many adjustments to the positions of the wheel sets to ensure the hornguides lined up correctly with their respective axleboxes.
All was not plain sailing with the engine, with its pony truck centre pin, about 3 inches to one side of its corresponding bolster pin hole and this necessitated the use of our Armstrong screw travelling jacks as seen in the photo below. Once up in the air, the travelling screw enables whatever is up in the air to move sideways - within limits.
The rear of the loco also required shifting sideways, about 1 inch in the opposite direction. Slow and careful lowering enabled all spring pins to be fitted so that at the end of the day the engine was sitting on its own wheels with all weight taken by its own springs. The engine was noticeably higher off the ground, as would be expected with thicker tyres.
While this has been some time coming and is good to see, it is tempered by the fact that there is still quite a lot of work to be done including some critical checks which must all end up with favourable results.
These include;
- the fact we had to move the positions of the axles, albeit slightly, is bound to have upset the crank pin centres in the rods and it is expected that offset rod bushes will be required to compensate for this.
- weight distribution could be anywhere at the moment so the weights on individual wheels have to be measured followed by somewhat difficult and time consuming adjustments. Initially this work will occur with the loco in its unladen condition, then after its test run to check bearings (see below), and the boiler has been filled, the weight distribution will need to be rechecked.
- all reworked pony truck and tender bearings have to be proved and this will happen via a simple test run.
- boiler inspections with firebox clothing removed, a full hot water hydro test to 220 psi followed by steam tests to check the long dormant boiler.
Realistically, there will be other items which come up to surprise and annoy us but hopefully they won't be too major.
A week earlier gave a report on another innovative manoeuver using dummy axles
Ron Gunn from Puffing Billy advised us that we should fit all axleboxes to their respective horn guides in their normal running position and make up 3 dummy axles incorporating a machined disc on each end to represent the exact diameter of each axle journal. The ends of the dummy axles have been centred and the axleboxes wedged hard up against the leading hornguides. Then using trammels, the spacing of the axles can be found quite accurately when measured from side to side and compared thus indicating if the axles are square to the piano wire, the frame and hence the track. The following photos show the setup.
We have been busy most of the week doing all this and have confirmed the earlier diagnosis that the driving and trailing axles are misaligned and by amounts considered by Ron G to be excessive. So now we know exactly what the errors are and can make corrections by either grinding or shimming the horn guides as may be required. Once that part is completed, the next major task is to realign the slidebars to complement the realigned axles.
This updated an eartlier more lengthy report a week earlier
Progress today included removing both front pony mudguards and main cylinder covers. Both piston rods were disconnected from their crossheads and rod packing assemblies removed followed by the pistons - fair bit of carbon around as. Butch has started setting up the gizmos to hold and locate the piano wires through the cylinders to the rear of the frame.
Our best air jack was used to lift the loco at roughly its centre point separately on each side to encourage the main frame to spring upwards a little to refit the hornblock binders. Bit amazing to watch the binder lugs move closer together as the jack did its business so all binders are temporarily refitted as they are required to be for the frame measuring work. The loco has been levelled front and back longitudinally and laterally using BJ's laser levels - marvellous little gadgets that tell you instantly and exactly how things are sitting in the world. JL turned up at the wrong time for him as I suggested how great it would be for SR to have such levels on hand. Caliper and laser measuring has confirmed the pony trunnion is around 5 mm to the right of the centre of the loco using both sides of the frame as datum points. This in itself could be part or all of the reason why 207 is not right, however no-one is jumping to conclusions on that until a lot more measurements have been confirmed against the piano wires.
Our fitter, Shaun Cassidy, has completed machining and welding a new tender brake cylinder piston ), the existing one having been written off by our inspector as being well past its effective use by date due to being old cast iron and difficult to successfully repair its cracks by brazing.
The next task involved use of dummy axles. Ron's suggestion was to fit all axleboxes to their respective horn guides in their normal running position and make up 3 dummy axles incorporating a machined disc on each end to represent the exact diameter of each axle journal. Then using trammels, the spacing of the axles can be found quite accurately when measured from side to side and compared thus indicating if the axles are square to the piano wire, the frame and hence the track. This confirmed the earlier diagnosis that the driving and trailing axles are misaligned and by amounts considered by Ron to be excessive. So now we know exactly what the errors are and can make corrections by either grinding or shimming the horn guides as may be required.
Previously I mentioned that things looked out of whack when measurements were taken to ensure 207's driving wheel set would line up properly when the engine was lowered onto them. And the more work we did to seek some answers, lots more confusing inconsistencies were found. Not surprising because Ron's inspections and assessments showed there are a number of contributing issues. Ron's thoughts are that the loco has seen a lot of hard slogging work which can only go back to its SAR days and we know this was common practice then. One task he advised was to recheck the rebuilt pony truck about its own centreline to ensure the wheels were equally spaced from the centreline and that the axles were square to the frame. Shaun has completed this work and all was found to be OK. Briefly the main issues are;
- trailing driver horn guides are not square to the frame - by quite a bit. Not one bit surprising and we suspect this to be part of the reason for the abnormal flange wear and also the thump from that area. Remedial work will require grinding and shimming of existing hornguides. To complete the total picture, all axleboxes will be lifted into the frame to ensure their correct fit with their guides, then a dummy axle fitted to each set to ensure they are parallel to each other and square in the frame.
- all four slidebars are misaligned to the piano wire so these require realigning to complement the realigning of the driver axles.
- all six driver bearings are worn to such an extent they are being hammered back and forth and obviously more so when the loco is being worked hard. These will have to be completely renewed sometime next year. Until then, the loco will be limited to light work - CT duties only.
- the top oil grooves in all driver bearings need relief along their sharp edges to increase the ability of the oil to gain access to the bearings.
Not directly part of the original problems but still issues which are to be attended to at this time are;
- the hard chroming on both piston rods has worn through, so much so that on the LH rod corrosion of the rod has started.
- the RH piston packing has suffered wire drawing from leaks and needs to be replaced.
- all piston rings are stuffed with ring gaps up to whopping 3/4" instead of the nominated 3/32" max. Fortunately the ovalities and tapers in the cylinders are within limits to re-ring plus the piston heads are still of sufficient diameter when compared to the cylinder bores.
- welding repairs required on two horn guide binders.
The first 3 of those just above only became evident when the pistons were removed to fit the piano wires. The earlier thoughts that there were troubles with the pony trunnion in both location and OD have proved to be false. The trunnion is not off centre when related to the piano wires and the measured clearance between trunnion and bolster is surprisingly within drawing limits.
Early Jan 2011
Another significant milestone on 7th January
The loco was moved from road 4 at Mt Barker Depot to over the pit on road 5. There were a few initial concerns with the LHS coupling rods tightening up a bit for about 1/3 of the wheel turn but as a number of compromises had to be put in place to minimise some remaining misalignments, it is something we will live with, provided no crankpins run too warm on the trail run.
Once over the pit, an indication of the weight on each wheel was measured using the Porta Power and a 10000 psi pressure gauge calibrated to one of our hydraulic rams. Once a technique had been developed to overcome "stiction" in the heavy leaf springs, consistent results were obtained after allowing for the fact the loco is somewhat lighter with a good part of its components yet to be fitted and the boiler to be filled. The overall results showed that at this stage only 1 tonne has to be redistributed from the driving and trailing axles onto the pony truck and this should be fairly easy to accomplish by rejigging the pony truck spacer plates. The most significant tasks then remaining before a trial run are to undertake an Equipment Leakage Test on the tender air brake system and to connect the engine to the tender.
Andrew Gramp's "action shot" shows volunteer John Gordon applying the Armstrong Test on the rods
Again it must be appreciated that each milestone is good progress but the reworked pony and tender axlebox bearings (12 altogether) and boiler still have to pass all tests with satisfactory results.
Much work has been carried out on 207 since December 2010. With adjustments to the slide bars, axles box horn guides and pony centre completed, the engine was lowered onto its wheels. Wear in the piston rings and on piston rods required the outsourcing of re-machining the piston ring groves and the manufacture of new piston rings. The piston rods were ground and hard chromed.
Tightness in the left leading and trailing coupling rod bushes was apparent and overcome by the machining and installation of an eccentric sleeve and fitted to the leading crank pin with slight reworking of other crank pin bushes.
Refitting of all brake gear to the tender along with air tests of the tender brakes, permitted a successful trial run on 14/01 to Strathalbyn using DE507 and 958. Some excessive heat was detected on the return journey in the leading pony axle boxes which required removal for inspection. Slightly tight tolerances in the re-metalled hub liners required light machining to overcome the heat build up.
Refitting of all air pipes, blow down pipe, brake rigging, injector water and overflow pipes, ash pan doors (with some reworking) valve eccentrics and rods, including expansion links is complete.Outer firebox clothing has been removed in preparation for a hot water hydro testing and inspection revealing some concerning wastage to the top firebox outer plate. Thickness testing has been performed and accepted by the boiler inspector however there is a considerable amount of wastage. The measurements will be logged and used to monitor the plate. The corrosion appears to be caused by rouge whistle condensate and rains from any overnight storage in outside areas being trapped under the boiler clothing.
Replacement timber insulation has been made to insulate the firebox as the existing timbers have suffered and broken up due to heat stress.
Upon successful boiler hydro and steam testing final fitting and boiler clothing will be reinstated for the first test run in steam.
January 2011
Earlier; Rx207 on its wheels and off to Strathalbyn
Much work had been carried out on Rx207 since December. With adjustments to the slide bars, axles box horn guides and pony centre completed, the engine was lowered onto its wheels. Wear in the piston rings and on piston rods required the outsourcing of re-machining the piston ring groves and the manufacture of new piston rings. The piston rods were ground and hard chromed. Tightness in the left leading and trailing coupling rod bushes was apparent and overcome by the machining and installation of an eccentric sleeve and fitted to the leading crank pin with slight reworking of other crank pin bushes.
Refitting of all brake gear to the tender along with air tests of the tender brakes, permitted a successful trial run 14th January when the loco was hauled tender first at track speed to Strathalbyn using DE507 and 958 with stops on the down at Fidlers Lane, Philcox Hill, Bugle Ranges, Gemmells and Strath. This movement went well with just a little bit of warmth from two crank pins. On the return the first stop was at Philcox Hill so as the bearings would undergo a good 40 mins of running at mostly 40 kph. The "outing" was organised by Ian Johnston, who has been providing most of the regular reports on progress on the loco's rebuild, supported by Craig Dunstan, Shaun Cassidy, Peter Soar, Andrew Gramp and Ron Norrell most of whom feature in the photos at the top of this page.
Some excessive heat was detected on the return journey in the leading pony axle boxes which required removal for inspection. Slightly tight tolerances in the re-metalled hub liners required light machining to overcome the heat build up. Refitting of all air pipes, blow down pipe, brake rigging, injector water and overflow pipes, ash pan doors (with some reworking) valve eccentrics and rods, including expansion links is complete.
A week or previously the Rx had been able to see daylight again when the loco was moved from road 4 at Mt Barker Depot to over the pit on road 5.
There were a few initial concerns with the LHS coupling rods tightening up a bit for about 1/3 of the wheel turn but as a number of compromises had to be put in place to minimise some remaining misalignments, it is something we will live with, provided no crankpins run too warm on the trial run.
Andrew Gramp caught Rx207 out in the sunshine (right) with the "experts" checking the tightness in the LHS coupling rods and deciding to leave them and see how they go in the first trial run
Once over the pit, an indication of the weight on each wheel was measured using the Porta Power and a 10000 psi pressure gauge calibrated to one of our hydraulic rams. Once a technique had been developed to overcome "stiction" in the heavy leaf springs, consistent results were obtained after allowing for the fact the loco is somewhat lighter with a good part of its components yet to be fitted and the boiler to be filled.
The overall results showed that at this stage only 1 tonne had to be redistributed from the driving and trailing axles onto the pony truck and this was fairly easily accomplished by rejigging the pony truck spacer plates. The most significant tasks then remaining before a trial run were to undertake an Equipment Leakage Test on the tender air brake system and to connect the engine to the tender.
These and earlier stages of the rebuilding can be followed
by reading a series of comprehensive reports prepared by Ian Johnston,
accompanied by a collection of interesting photos. (see below)
This milestone was reached on Friday 14th January when the loco was hauled at track speed to Strathalbyn and return between diesels 507 and 958, including a good 40 mins of running at mostly 40 kph, subsequent inspection by our Boiler Inspector identified a significant level of corrosion to various boiler fittings, most of which was able to be rectified but took lots of extra time and effort.
The loco was then subjected to a 90psi cold water hydro test which not unexpectedly indicated a number of leaks which would require much higher pressure testing before full certification can be granted.
Andrew Gramp's photos show the loco team inspecting the Rx at a planned stop enroute on the Febuary 14th jaunt and the three unit consist safely standing in Strathalbyn yard before it returned "up the hill"
to read his words
|
February 2011
220psi!
Following the last lot of hic cups with corroded studs and one rotten element plus needing to procure a Metaflex gasket by overnight air freight from Sydney for the blow down valve, all was ready for the hot water hydro to 220 psi on Wednesday 23rd. At about 0905 hrs, smoke appeared from 207's funnel for the first time in almost 4 years which was pleasing to all.
Some bush plumbing was put together to circulate the boiler water during the heating process to ensure as much as possible that the temperature of the boiler water was fairly even from top to bottom and end to end. The water was taken from the bottom blowdown valve and pumped back in via the vent valve on top of the boiler behind the funnel. This seemed to work quite well. By about 1100 hrs the water temp was stable on 65 deg C so it was time to remove the circulating plumbing and connect the hydro pump and its plumbing work. There was about a 1/2 hr delay with leaking valves in the pump but once sorted, the boiler pressure was gradually raised to 220 psi and held at that pressure for the minimum 30 mins and here's the evidence!!!.
The boiler looked good with no leaks from the boiler itself which pleased Bernie D, our inspector. What did not please us though was the unacceptable amount of water flowing from the cylinder release cocks indicating some sort of leak from either the regulator, J pipe, or heaven forbid, the internal steam pipe. This leak had been present to a minor degree during the 100 psi hydros and it became a case of hoping and wishing it did not get any worse at the higher pressure.
As a result a decision was soon made to drop the pressure, take off the dome cover and remove both the regulator and J pipe to inspect for any indications of why there is this largish leak. No immediate signs.
The next morning, the first investigative hydro test proved the internal steam pipe was OK. The J pipe gasket showed no signs of leakage so yesterday's leaks could only have come from the regulator. Butch spent most of the morning blueing and scraping to provide as water tight fit as possible. The good news is that a subsequent 100 psi hydro proved the regulator is now as good as new with the boiler holding 100 psi by itself for a number of minutes.
The next stage is the steam test to set the safety valves and check the operation of the air compressor, injectors, lubricator, sanders, whistle and electrical system. PC has rebuilt the turbo and on air it works as good as gold. The most likely candidates to give trouble are the lubricator and air compressor in that order as they have stood idle for some time, with the former having a lousy history of blocking up and refusing to work under these circumstances. Obviously all accessories have to operate properly before we can say the loco is getting close to being ready. Also the previously hot running pony truck bearings have not been tried and proven although I think we would be unlucky to have further troubles.
A milestone hot water hydro to 220 psi was conducted on Wednesday 23rd. At about 0905 hrs, smoke appeared from 207's funnel for the first time in almost 4 years which was pleasing to all and here's the evidence to prove it.
The water pressure was raised to 220 psi and held at that pressure for the minimum 30 mins. The boiler looked good with no leaks from the boiler itself which pleased our inspector.
However an unacceptable amount of water flowing from the cylinder release cocks meant that on Thursday 24th our fitter spent most of the morning blueing and scraping to provide as water tight fit as possible with the good news being that a subsequent 100 psi hydro proved the regulator is now as good as new with the boiler holding 100 psi by itself for a number of minutes.
The next stage was the steam test to set the safety valves and check the operation of the air compressor, injectors, lubricator, sanders, whistle and electrical system. Obviously all accessories have to operate properly before we can say the loco is finally ready. Also the previously hot running pony truck bearings have to be proven although we think we would be unlucky to have further troubles.
March 2011
With congratulations all round to our mechanical services team we can finally announce that our 1913 vintage loco Rx207 "Dean Harvey" pased its trial run from Goolwa to Victor Harbor on the 6th March and with just a few minor "tune ups" to go will return to our regular services within a few days.
The loco had been transferred "dead" to Goolwa Depot the previous week using DE958 in order to avoid a closure of the line from Mt Barker due to bridge infrastructure work.
In spite of extra-ordinary efforts by our loco team, it was not possible to have the loco available for the Goolwa Wooden Boat Festival in late February, but the loco was towed by DE958 from Mt Barker to Goolwa Depot on February 27th for final adjustments and test running during the following week.
All going well, it is proposed to run the loco on selected dates initially March 13th, 14th and 27th and then during the April school holidays. Watch our website for latest details as these dates may change.
April 2010
- Tender wheels have returned to MB depot - cleaned for crack testing of axles
- Tender bogies cleaned and identified a number of loose rivets under bogie centres
- Bogies centres removed and crack tested
- Bogie centre transoms cleaned and cracked tested
- Loose rivets blown out by oxy for replacing with fitted bolts
- Tender springs and springs hanger links removed for inspection of pins and bushes All pins and bushes have suffered excessive wear requiring all new link bushes to be machined and installed, all spring eyelets to be machined, all new link hanger tapered bushes to be machined. Most of these components were either renewed or refurbished in the 2000 overhaul.
- All link and engine frame bush holes being reamed to standardise bush size.
- 3 worn engine axle box horn guides have been repaired by welding up and face grinding.
- Rear engine spring compensating beam bushes being renewed
- Worn compensating beam ends being welded and ground
- Engine spring/axle box hanger holes being welded to remove ovality and rebored - all engine spring pin work being performed by Lindsay Research and Development Engineering.
- Pony truck axle box fitting is currently underway with many hours being spent hand scraping the rebuild bearing shells.
- A new ash pan damper door has been made to replace the badly wasted door
- Severely wasted sections of the ash pan have been removed and new sections welded in
- Blow down valve removed for inspection of the mounting studs - studs to be renewed due to poor condition
- All firebox corner wash out plug hole threads have been inspected with one plug hole requiring tapping and fitting of a larger plug if possible
- All firebox corner wash out holes radius boiler plates and blow down hole have been cleaned for crack testing
- All driving wheel and pony wheel sets axles have been polished for crack testing
- Upon return of all springs, pins and links to MB depot reassembly of the loco's running gear can commence
Our photos show volunteer David Groves welding repairs to Rx207's axle box horn guides and the locos retyred driving wheels waiting for fitting of axle boxes and springs.
March 2012
Rx207 was withdrawn from service in February and returned to Mt Barker for attention to its firebox arch.
Obtaining a suitable refractory has been a long story in itself but as is usual the material we used previously was no longer available. Its substitute was not recommended for casting by trowelling. We eventually found an excellent brew suitable for trowelling and a continuous temperature rating of 1400 deg C. However it took some weeks to sort all this out and get the stuff and instructions delivered from interstate.
Casting of complete arches for small power locos, instead of using numerous bricks like in the SAR days is nothing new for the SHR – from memory we first started them in the late 1980s. An Rx arch would contain about 50 bricks which all had to be individually cast, then cemented together in the firebox to form the brick arch. While casting the arch is a solid 2 hour job, it would probably still take longer to build the arch from all the bricks let alone having to cast them one by one.
A steel former plate designed many years ago by Ron Williams with supporting timbers underneath for the new firebox arch was fitted.
The front edge of the arch is somewhat thicker than the one it replaced. This should provide a larger heatsink and maintain better firebox heat, particularly when the loco is standing at stations between movements.
There was a fairly long curing and preheating process required for the new arch. There is a preferred time of 48 hours before the former can be removed, then another 48 hours air drying followed by a prescribed heating cycle. The first part of the cycle uses a fan heater in the firebox then a small kindling fire on the grates. If any of this is undertaken too quickly, the still trapped moisture in the arch turns to steam and the arch can explode.
The photos below show the casting supported initially by the former plate and in its final cured state
|