[IMAGE] "From the Footplate" - SteamRanger's Enthusiast Website    

Latest Loco Status

Steam Locos

Diesel Locos

Infrastructure

Rollingstock Maintenance

 

HOME PAGE


  Enthusiast Activities - Looking Back at Loco Maintenance Tasks


This page describes major maintenance and rehabilitation work undertaken on our historic rolling stock over recent years
using mainly our volunteer resources

The information draws upon informal reports provided by various members of the merchanical services team, particularly from Ian Johnston,
and may at times be repetitive but provides a useful "blow by blow" summary of the erxtensive work undertaken

CLICK HERE to read about current maintenance tasks




Rx207




Progress Report February 2013

The Mechanical Services Manager has provided the following overview of what work is being carried out on this loco following its withdrawal from operational service after the Christmas 2012 - New Year Cockle Train running which it shared with loco 621

"Rx207 has been returned to Mt Barker for assessment as to its condition and appropriate remedial action and hopefully will be back on the tracks in October / November 2013. The Boiler is being removed for repairs to rivets around the foundation ring at the base of the firebox due to age wastage. Also there is some boiler plate of the inner firebox throat plate / front plate that has some thin spots that have began to show cracks thus requiring some sections to be replaced.

The worn driving wheel axle bearings that were not renewed during the re-tyre job are to be cast and renewed whilst the boiler is off the frame. The axle journals will have some slight taper machined out and the new bronze bearings will be cast and then machined to suit.

Time and a shortage of funds did not permit this task previously and the loco was returned to service expecting that within 3 years the boiler may have to come off for some of the current work so the bearings would hopefully last that long. The chance was taken and it turned out that the thinning plate caught up first."

Future work in 2013 will involve new baffles in the tender water space and work around the boiler foundation ring.

At the moment it appears 207's 2in. diameter dump grate support shaft has again bent from the affects of heat and the use of the ash wetter causing the dump grate to drop thereby exposing the foundation ring rivet heads to the fire. This is a "no no" because the rivets do not have water behind them to take away the heat and prevent them from being burnt.

207's droopy dump grate was fairly easily fixed. the support links were lenthened by a bit over an inch However while ferreting around underneath we noticed a very wet spot in the RH corner of the inner firebox.

Cleaning and drying the spot soon revealed a 1/2" long horizontal crack in the boiler plate coinciding with the top of the foundation ring on the other side of the plate where, traditionally, grooving occurs in the plate on the water side so the leak is no real surprise.

Such cracks automatically fail the loco so decisions have to be made with the Boiler Inspector as to whether the crack can be effectively temporarily fixed or that part of the boiler has passed its use by date considering the other issues including 5 wasted and leaky rivet heads. The Boiler Inspector requires the boiler to be removed from the frame after April 2013 for a complete inspection.

The frame also will be lifted from wheels for axle-box / wheels inspection.

These photos taken by Peter Michalak at Mt Barker Depot in April 2013 show Rx207 preparing for a boiler lift


And a Boiler Lift - May 14th - a report from Ian Johnston

A few photos are included below showing 207’s boiler finally being lifted from its frame

Because of the roof height restrictions the boiler could not be lifted cleanly out of 207’s frame so it was lifted part way so as to clear the top of the frame then the frame moved rearwards so as the boiler became completely clear and could be moved back towards the two cranes used. Since the cranes were then occupying the spot designated for the boiler, the boiler was temporarily left on the ground while the front and rear boiler supports were put in place. The two cranes were repositioned so that the boiler could be slewed and carefully placed on the supports.

A temporary sleeper sty has been placed under the outer throatplate as a precaution but as this is the spot where most of the repair work is required, a more permanent sty will be erected under the centre of the boiler.

Interesting in the centre photo , where the boiler is about to land on its supports, markings on the side of the firebox from 2000 for “this way up” and “keep dry” are still there!! Also to the rear of the firebox in the top 3 rows of stays can be seen a festering patch from leaky stay cups so it has been a timely exercise to find them. The third photo shows what a mess steam locos can be underneath with one highlight being the grotty looking ashpan and the perennial “whoof” in the dump grate shaft being easy to spot.

       


Those assisting in this work were Butch Cassidy, Daryl Simon, Trevor Sasche, Rod Stone and Nev. Pauley so many thanks to them.

And some more news - late July 2013 - a further report from Ian Johnston

It has been a while since we separated 207’s boiler from the engine and work has steadily progressed as resources permit keeping in mind there is always plenty to do in just keeping the operational trains on the move.

The plan with the boiler has been to progressively investigate all known and possible additional problem areas. This initially involved taking over 260 thickness measurements of boiler plates, principally of the lower sections of the inner firebox (both side sheets and tubeplate) and the outer plates (both wrapper and throat plates). Measurements were taken on the front half of the firebox where the known problem areas were but then also extended both towards the rear of the boiler and upwards from the foundation ring until acceptable plate thicknesses were consistently found. The measurements revealed the usual issues with locomotive boilers in that there was lots of plate wastage between the foundation ring rivet heads and in the plates for up to 150 mm above the ring. Under guidance from Boiler Inspector, Bernie Dickinson, small sections of suspect plate were progressively cut out for further visual inspections to eventually determine the full scope of the work. This work also included the removal of several flexible and rigid stays and many rivets around the foundation ring.

The main issues highlighted have included;
      - the condition of all plates on the water side was quite good indicating that our water treatment regimes are keeping corrosion to a minimum.
      - wastage of the inner firebox side sheets between the ring rivets due mainly to ashes trapped between the sheets and the firegrate carriers.
      - both front corners of the inner firebox were cracked on the water side due to the prolonged thermal shocks over the years.
      - wastage of the outer wrapper and throatplates between the ring rivet heads, this time due to outside sources of water like rain,
        boiler washouts, blowdowns etc.
     - most of the rivets around the front half of the ring had suffered excess corrosion resulting in their heads not being as effective as desired.
     - The foundation ring is in good condition even though it is original from when this boiler was built in 1932.

The photos attached show the very first section cut from the outer throatplate for the first inspection and evaluation (first photo) with subsequent shots depicting where we are currently at. A meeting with our inspector will determine if we have reached the full scope of work required. The foundation ring is in good condition even though it is original from when this boiler was built in 1932.



Outer throatplate (first cut) ---------- Outer throatplate ---------- LH Wrapper plate


RH Wrapper plate ----------- Inner Firebox ------------ LH corner Wrapper plate


All photos: Ian Johnston

Late September 2010


Which follows on from a report in late September from Mechanical Services Manager, Craig Dunstan

At last so much of the hard work that has been put in by all involved over the past 3 1/2 years is now starting to take shape. With the recent introduction of a full time fitter back into the MB workshop and being complimented by dedicated volunteers, has seen Rx207 move ahead again in leaps and bounds with work concentrating on Rx207 5 - 6 days per week.

As can be seen in these photos the engine's pony truck has been reassembled on road 4 then to be repositioned back under the engine. Many modifications have been made by introducing grease lubrication to all of the pony truck moving components that previously just relied upon the hope that components received a "hopeful" drip of oil from somewhere, that generally got sucked up by some dirt or dust and never generally made it into its intended place. If so it did not remain there for very long which was apparent by the many worn pins, bushes and shafts. Likewise the existing oil lubricated bogie centre will be converted to grease lubrication with some minor modifications to suit.

   

The tender wheels were finally reunited with the bogie frames after complete rebuilding of the tender axles box bearings (they roll beautifully with ease) and replacement of two axle boxes due to considerable cracking of the box lower halves or oil pans. Two suitable boxes were obtained from 207's original bogies and machined to suit. Suitable replacement boxes will need to be sourced when rebuilding the bogies for Rx224.

Again like the pony truck, the tender spring links have been re-bushed with a complete new set of spring link pins being manufactured with the inclusion of grease lubrication thus doing away with the existing oil system. Upon disassembly all spring link pins and bushes exhibited considerable wear requiring replacement. The tender bogie centres have also received some minor reworking to accept grease lubrication as opposed to the forever blocking oil system.

   

Further work will see the completion of bogie painting and fitting of axle horn binders etc, with the bogies set then to be placed back under the tender. Work will then progress to the setting out of the engine axle boxes to install a dust shield system and beginning to reassembling the axle boxes, springs and coupling rods onto the driving axles.

The engines blow down valve is currently undergoing overhaul to the valve and seat with the introduction of o'ring sealing to the shaft and end cap in attempts to eliminate the unwanted water spraying back across the boiler throat plate and ash pan damper areas. New blow down valve studs have been manufactured and installed in the throat plate.

Late October 2010

In late October Ian Johnston reported

Recent work on 207 has included removing both front pony mudguards and main cylinder covers. Both piston rods were disconnected from their crossheads and rod packing assemblies removed followed by the pistons - fair bit of carbon around as. Butch has started setting up the gizmos to hold and locate the piano wires through the cylinders to the rear of the frame.

Our best air jack was used to lift the loco at roughly its centre point separately on each side to encourage the main frame to spring upwards a little to refit the hornblock binders. Bit amazing to watch the binder lugs move closer together as the jack did its business so all binders are temporarily refitted as they are required to be for the frame measuring work.The loco has been levelled front and back longitudinally and laterally using laser levels - marvellous little gadgets that tell you instantly and exactly how things are sitting in the world.

Caliper and laser measuring has confirmed the pony trunnion is around 5 mm to the right of the centre of the loco using both sides of the frame as datum points. This in itself could be part or all of the reason why 207 is not right, however no-one is jumping to conclusions on that until a lot more measurements have been confirmed against the piano wires.

As another project our fitter Butch has completed machining and welding a new tender brake cylinder piston (photos right), the existing one having been written off by our inspector as being well past its effective use by date due to being old cast iron and difficult to successfully repair its cracks by brazing.

Late December 2010



One of our major milestones was accomplished on the 3rd December with 207 landing back on its wheels and on track. All the realignment work seems to have been in the right direction as everything fitted together very nicely without any real hassles. However there was still a lot work required to get the engine back over the centre of the track and many adjustments to the positions of the wheel sets to ensure the hornguides lined up correctly with their respective axleboxes.

All was not plain sailing with the engine, with its pony truck centre pin, about 3 inches to one side of its corresponding bolster pin hole and this necessitated the use of our Armstrong screw travelling jacks as seen in the photo below. Once up in the air, the travelling screw enables whatever is up in the air to move sideways - within limits.

The rear of the loco also required shifting sideways, about 1 inch in the opposite direction. Slow and careful lowering enabled all spring pins to be fitted so that at the end of the day the engine was sitting on its own wheels with all weight taken by its own springs. The engine was noticeably higher off the ground, as would be expected with thicker tyres.

While this has been some time coming and is good to see, it is tempered by the fact that there is still quite a lot of work to be done including some critical checks which must all end up with favourable results.

These include;

  • the fact we had to move the positions of the axles, albeit slightly, is bound to have upset the crank pin centres in the rods and it is expected that offset rod bushes will be required to compensate for this.
  • weight distribution could be anywhere at the moment so the weights on individual wheels have to be measured followed by somewhat difficult and time consuming adjustments. Initially this work will occur with the loco in its unladen condition, then after its test run to check bearings (see below), and the boiler has been filled, the weight distribution will need to be rechecked.
  • all reworked pony truck and tender bearings have to be proved and this will happen via a simple test run.
  • boiler inspections with firebox clothing removed, a full hot water hydro test to 220 psi followed by steam tests to check the long dormant boiler.

Realistically, there will be other items which come up to surprise and annoy us but hopefully they won't be too major.


A week earlier gave a report on another innovative manoeuver using dummy axles

Ron Gunn from Puffing Billy advised us that we should fit all axleboxes to their respective horn guides in their normal running position and make up 3 dummy axles incorporating a machined disc on each end to represent the exact diameter of each axle journal. The ends of the dummy axles have been centred and the axleboxes wedged hard up against the leading hornguides. Then using trammels, the spacing of the axles can be found quite accurately when measured from side to side and compared thus indicating if the axles are square to the piano wire, the frame and hence the track. The following photos show the setup.



We have been busy most of the week doing all this and have confirmed the earlier diagnosis that the driving and trailing axles are misaligned and by amounts considered by Ron G to be excessive. So now we know exactly what the errors are and can make corrections by either grinding or shimming the horn guides as may be required. Once that part is completed, the next major task is to realign the slidebars to complement the realigned axles.


This updated an eartlier more lengthy report a week earlier

Progress today included removing both front pony mudguards and main cylinder covers. Both piston rods were disconnected from their crossheads and rod packing assemblies removed followed by the pistons - fair bit of carbon around as. Butch has started setting up the gizmos to hold and locate the piano wires through the cylinders to the rear of the frame.

Our best air jack was used to lift the loco at roughly its centre point separately on each side to encourage the main frame to spring upwards a little to refit the hornblock binders. Bit amazing to watch the binder lugs move closer together as the jack did its business so all binders are temporarily refitted as they are required to be for the frame measuring work. The loco has been levelled front and back longitudinally and laterally using BJ's laser levels - marvellous little gadgets that tell you instantly and exactly how things are sitting in the world. JL turned up at the wrong time for him as I suggested how great it would be for SR to have such levels on hand. Caliper and laser measuring has confirmed the pony trunnion is around 5 mm to the right of the centre of the loco using both sides of the frame as datum points. This in itself could be part or all of the reason why 207 is not right, however no-one is jumping to conclusions on that until a lot more measurements have been confirmed against the piano wires.

Our fitter, Shaun Cassidy, has completed machining and welding a new tender brake cylinder piston ), the existing one having been written off by our inspector as being well past its effective use by date due to being old cast iron and difficult to successfully repair its cracks by brazing.


   

The next task involved use of dummy axles. Ron's suggestion was to fit all axleboxes to their respective horn guides in their normal running position and make up 3 dummy axles incorporating a machined disc on each end to represent the exact diameter of each axle journal. Then using trammels, the spacing of the axles can be found quite accurately when measured from side to side and compared thus indicating if the axles are square to the piano wire, the frame and hence the track. This confirmed the earlier diagnosis that the driving and trailing axles are misaligned and by amounts considered by Ron to be excessive. So now we know exactly what the errors are and can make corrections by either grinding or shimming the horn guides as may be required.

Previously I mentioned that things looked out of whack when measurements were taken to ensure 207's driving wheel set would line up properly when the engine was lowered onto them. And the more work we did to seek some answers, lots more confusing inconsistencies were found. Not surprising because Ron's inspections and assessments showed there are a number of contributing issues. Ron's thoughts are that the loco has seen a lot of hard slogging work which can only go back to its SAR days and we know this was common practice then. One task he advised was to recheck the rebuilt pony truck about its own centreline to ensure the wheels were equally spaced from the centreline and that the axles were square to the frame. Shaun has completed this work and all was found to be OK. Briefly the main issues are;

  • trailing driver horn guides are not square to the frame - by quite a bit. Not one bit surprising and we suspect this to be part of the reason for the abnormal flange wear and also the thump from that area. Remedial work will require grinding and shimming of existing hornguides. To complete the total picture, all axleboxes will be lifted into the frame to ensure their correct fit with their guides, then a dummy axle fitted to each set to ensure they are parallel to each other and square in the frame.
  • all four slidebars are misaligned to the piano wire so these require realigning to complement the realigning of the driver axles.
  • all six driver bearings are worn to such an extent they are being hammered back and forth and obviously more so when the loco is being worked hard. These will have to be completely renewed sometime next year. Until then, the loco will be limited to light work - CT duties only.
  • the top oil grooves in all driver bearings need relief along their sharp edges to increase the ability of the oil to gain access to the bearings.

Not directly part of the original problems but still issues which are to be attended to at this time are;

  • the hard chroming on both piston rods has worn through, so much so that on the LH rod corrosion of the rod has started.
  • the RH piston packing has suffered wire drawing from leaks and needs to be replaced.
  • all piston rings are stuffed with ring gaps up to whopping 3/4" instead of the nominated 3/32" max. Fortunately the ovalities and tapers in the cylinders are within limits to re-ring plus the piston heads are still of sufficient diameter when compared to the cylinder bores.
  • welding repairs required on two horn guide binders.

The first 3 of those just above only became evident when the pistons were removed to fit the piano wires. The earlier thoughts that there were troubles with the pony trunnion in both location and OD have proved to be false. The trunnion is not off centre when related to the piano wires and the measured clearance between trunnion and bolster is surprisingly within drawing limits.


Early Jan 2011

Another significant milestone on 7th January

The loco was moved from road 4 at Mt Barker Depot to over the pit on road 5. There were a few initial concerns with the LHS coupling rods tightening up a bit for about 1/3 of the wheel turn but as a number of compromises had to be put in place to minimise some remaining misalignments, it is something we will live with, provided no crankpins run too warm on the trail run.

Once over the pit, an indication of the weight on each wheel was measured using the Porta Power and a 10000 psi pressure gauge calibrated to one of our hydraulic rams. Once a technique had been developed to overcome "stiction" in the heavy leaf springs, consistent results were obtained after allowing for the fact the loco is somewhat lighter with a good part of its components yet to be fitted and the boiler to be filled. The overall results showed that at this stage only 1 tonne has to be redistributed from the driving and trailing axles onto the pony truck and this should be fairly easy to accomplish by rejigging the pony truck spacer plates. The most significant tasks then remaining before a trial run are to undertake an Equipment Leakage Test on the tender air brake system and to connect the engine to the tender.

Andrew Gramp's "action shot" shows volunteer John Gordon applying the Armstrong Test on the rods

Again it must be appreciated that each milestone is good progress but the reworked pony and tender axlebox bearings (12 altogether) and boiler still have to pass all tests with satisfactory results.




Much work has been carried out on 207 since December 2010. With adjustments to the slide bars, axles box horn guides and pony centre completed, the engine was lowered onto its wheels. Wear in the piston rings and on piston rods required the outsourcing of re-machining the piston ring groves and the manufacture of new piston rings. The piston rods were ground and hard chromed. Tightness in the left leading and trailing coupling rod bushes was apparent and overcome by the machining and installation of an eccentric sleeve and fitted to the leading crank pin with slight reworking of other crank pin bushes.

Refitting of all brake gear to the tender along with air tests of the tender brakes, permitted a successful trial run on 14/01 to Strathalbyn using DE507 and 958. Some excessive heat was detected on the return journey in the leading pony axle boxes which required removal for inspection. Slightly tight tolerances in the re-metalled hub liners required light machining to overcome the heat build up.

Refitting of all air pipes, blow down pipe, brake rigging, injector water and overflow pipes, ash pan doors (with some reworking) valve eccentrics and rods, including expansion links is complete.Outer firebox clothing has been removed in preparation for a hot water hydro testing and inspection revealing some concerning wastage to the top firebox outer plate. Thickness testing has been performed and accepted by the boiler inspector however there is a considerable amount of wastage. The measurements will be logged and used to monitor the plate. The corrosion appears to be caused by rouge whistle condensate and rains from any overnight storage in outside areas being trapped under the boiler clothing.

Replacement timber insulation has been made to insulate the firebox as the existing timbers have suffered and broken up due to heat stress. Upon successful boiler hydro and steam testing final fitting and boiler clothing will be reinstated for the first test run in steam.



January 2011

Earlier; Rx207 on its wheels and off to Strathalbyn

Much work had been carried out on Rx207 since December. With adjustments to the slide bars, axles box horn guides and pony centre completed, the engine was lowered onto its wheels. Wear in the piston rings and on piston rods required the outsourcing of re-machining the piston ring groves and the manufacture of new piston rings. The piston rods were ground and hard chromed. Tightness in the left leading and trailing coupling rod bushes was apparent and overcome by the machining and installation of an eccentric sleeve and fitted to the leading crank pin with slight reworking of other crank pin bushes.

Refitting of all brake gear to the tender along with air tests of the tender brakes, permitted a successful trial run 14th January when the loco was hauled tender first at track speed to Strathalbyn using DE507 and 958 with stops on the down at Fidlers Lane, Philcox Hill, Bugle Ranges, Gemmells and Strath. This movement went well with just a little bit of warmth from two crank pins. On the return the first stop was at Philcox Hill so as the bearings would undergo a good 40 mins of running at mostly 40 kph. The "outing" was organised by Ian Johnston, who has been providing most of the regular reports on progress on the loco's rebuild, supported by Craig Dunstan, Shaun Cassidy, Peter Soar, Andrew Gramp and Ron Norrell most of whom feature in the photos at the top of this page.

Some excessive heat was detected on the return journey in the leading pony axle boxes which required removal for inspection. Slightly tight tolerances in the re-metalled hub liners required light machining to overcome the heat build up. Refitting of all air pipes, blow down pipe, brake rigging, injector water and overflow pipes, ash pan doors (with some reworking) valve eccentrics and rods, including expansion links is complete.

A week or previously the Rx had been able to see daylight again when the loco was moved from road 4 at Mt Barker Depot to over the pit on road 5.

There were a few initial concerns with the LHS coupling rods tightening up a bit for about 1/3 of the wheel turn but as a number of compromises had to be put in place to minimise some remaining misalignments, it is something we will live with, provided no crankpins run too warm on the trial run.

Andrew Gramp caught Rx207 out in the sunshine (right) with the "experts" checking the tightness in the LHS coupling rods and deciding to leave them and see how they go in the first trial run

Once over the pit, an indication of the weight on each wheel was measured using the Porta Power and a 10000 psi pressure gauge calibrated to one of our hydraulic rams. Once a technique had been developed to overcome "stiction" in the heavy leaf springs, consistent results were obtained after allowing for the fact the loco is somewhat lighter with a good part of its components yet to be fitted and the boiler to be filled.

The overall results showed that at this stage only 1 tonne had to be redistributed from the driving and trailing axles onto the pony truck and this was fairly easily accomplished by rejigging the pony truck spacer plates. The most significant tasks then remaining before a trial run were to undertake an Equipment Leakage Test on the tender air brake system and to connect the engine to the tender.

These and earlier stages of the rebuilding can be followed
by reading a series of comprehensive reports prepared by Ian Johnston,
accompanied by a collection of interesting photos. (see below)

This milestone was reached on Friday 14th January when the loco was hauled at track speed to Strathalbyn and return between diesels 507 and 958, including a good 40 mins of running at mostly 40 kph, subsequent inspection by our Boiler Inspector identified a significant level of corrosion to various boiler fittings, most of which was able to be rectified but took lots of extra time and effort.

The loco was then subjected to a 90psi cold water hydro test which not unexpectedly indicated a number of leaks which would require much higher pressure testing before full certification can be granted.

Andrew Gramp's photos show the loco team inspecting the Rx at a planned stop enroute on the Febuary 14th jaunt and the three unit consist safely standing in Strathalbyn yard before it returned "up the hill"

   


SOME TECHO INFO!     Mechanical Services Manager, Craig Dunstan,
has contributed a little information on Rx207's superheater elements
which have now been reinstalled as part of the locos rebuilding
to read his words

February 2011

220psi!

Following the last lot of hic cups with corroded studs and one rotten element plus needing to procure a Metaflex gasket by overnight air freight from Sydney for the blow down valve, all was ready for the hot water hydro to 220 psi on Wednesday 23rd. At about 0905 hrs, smoke appeared from 207's funnel for the first time in almost 4 years which was pleasing to all.

Some bush plumbing was put together to circulate the boiler water during the heating process to ensure as much as possible that the temperature of the boiler water was fairly even from top to bottom and end to end. The water was taken from the bottom blowdown valve and pumped back in via the vent valve on top of the boiler behind the funnel. This seemed to work quite well. By about 1100 hrs the water temp was stable on 65 deg C so it was time to remove the circulating plumbing and connect the hydro pump and its plumbing work. There was about a 1/2 hr delay with leaking valves in the pump but once sorted, the boiler pressure was gradually raised to 220 psi and held at that pressure for the minimum 30 mins and here's the evidence!!!.

The boiler looked good with no leaks from the boiler itself which pleased Bernie D, our inspector. What did not please us though was the unacceptable amount of water flowing from the cylinder release cocks indicating some sort of leak from either the regulator, J pipe, or heaven forbid, the internal steam pipe. This leak had been present to a minor degree during the 100 psi hydros and it became a case of hoping and wishing it did not get any worse at the higher pressure.

As a result a decision was soon made to drop the pressure, take off the dome cover and remove both the regulator and J pipe to inspect for any indications of why there is this largish leak. No immediate signs.

The next morning, the first investigative hydro test proved the internal steam pipe was OK. The J pipe gasket showed no signs of leakage so yesterday's leaks could only have come from the regulator. Butch spent most of the morning blueing and scraping to provide as water tight fit as possible. The good news is that a subsequent 100 psi hydro proved the regulator is now as good as new with the boiler holding 100 psi by itself for a number of minutes.

The next stage is the steam test to set the safety valves and check the operation of the air compressor, injectors, lubricator, sanders, whistle and electrical system. PC has rebuilt the turbo and on air it works as good as gold. The most likely candidates to give trouble are the lubricator and air compressor in that order as they have stood idle for some time, with the former having a lousy history of blocking up and refusing to work under these circumstances. Obviously all accessories have to operate properly before we can say the loco is getting close to being ready. Also the previously hot running pony truck bearings have not been tried and proven although I think we would be unlucky to have further troubles.

A milestone hot water hydro to 220 psi was conducted on Wednesday 23rd. At about 0905 hrs, smoke appeared from 207's funnel for the first time in almost 4 years which was pleasing to all and here's the evidence to prove it.

The water pressure was raised to 220 psi and held at that pressure for the minimum 30 mins. The boiler looked good with no leaks from the boiler itself which pleased our inspector.

However an unacceptable amount of water flowing from the cylinder release cocks meant that on Thursday 24th our fitter spent most of the morning blueing and scraping to provide as water tight fit as possible with the good news being that a subsequent 100 psi hydro proved the regulator is now as good as new with the boiler holding 100 psi by itself for a number of minutes.

The next stage was the steam test to set the safety valves and check the operation of the air compressor, injectors, lubricator, sanders, whistle and electrical system. Obviously all accessories have to operate properly before we can say the loco is finally ready. Also the previously hot running pony truck bearings have to be proven although we think we would be unlucky to have further troubles.

March 2011

With congratulations all round to our mechanical services team we can finally announce that our 1913 vintage loco Rx207 "Dean Harvey" pased its trial run from Goolwa to Victor Harbor on the 6th March and with just a few minor "tune ups" to go will return to our regular services within a few days.

The loco had been transferred "dead" to Goolwa Depot the previous week using DE958 in order to avoid a closure of the line from Mt Barker due to bridge infrastructure work.

In spite of extra-ordinary efforts by our loco team, it was not possible to have the loco available for the Goolwa Wooden Boat Festival in late February, but the loco was towed by DE958 from Mt Barker to Goolwa Depot on February 27th for final adjustments and test running during the following week.

All going well, it is proposed to run the loco on selected dates initially March 13th, 14th and 27th and then during the April school holidays. Watch our website for latest details as these dates may change.

April 2010


  • Tender wheels have returned to MB depot - cleaned for crack testing of axles
  • Tender bogies cleaned and identified a number of loose rivets under bogie centres
  • Bogies centres removed and crack tested
  • Bogie centre transoms cleaned and cracked tested
  • Loose rivets blown out by oxy for replacing with fitted bolts

  • Tender springs and springs hanger links removed for inspection of pins and bushes All pins and bushes have suffered excessive wear requiring all new link bushes to be machined and installed, all spring eyelets to be machined, all new link hanger tapered bushes to be machined. Most of these components were either renewed or refurbished in the 2000 overhaul.
  • All link and engine frame bush holes being reamed to standardise bush size.

  • 3 worn engine axle box horn guides have been repaired by welding up and face grinding.
  • Rear engine spring compensating beam bushes being renewed
  • Worn compensating beam ends being welded and ground
  • Engine spring/axle box hanger holes being welded to remove ovality and rebored - all engine spring pin work being performed by Lindsay Research and Development Engineering.
  • Pony truck axle box fitting is currently underway with many hours being spent hand scraping the rebuild bearing shells.

  • A new ash pan damper door has been made to replace the badly wasted door
  • Severely wasted sections of the ash pan have been removed and new sections welded in
  • Blow down valve removed for inspection of the mounting studs - studs to be renewed due to poor condition
  • All firebox corner wash out plug hole threads have been inspected with one plug hole requiring tapping and fitting of a larger plug if possible
  • All firebox corner wash out holes radius boiler plates and blow down hole have been cleaned for crack testing
  • All driving wheel and pony wheel sets axles have been polished for crack testing
  • Upon return of all springs, pins and links to MB depot reassembly of the loco's running gear can commence
     

Our photos show volunteer David Groves welding repairs to Rx207's axle box horn guides
and the locos retyred driving wheels waiting for fitting of axle boxes and springs.



March 2012


Rx207 was withdrawn from service in February and returned to Mt Barker for attention to its firebox arch.

Obtaining a suitable refractory has been a long story in itself but as is usual the material we used previously was no longer available. Its substitute was not recommended for casting by trowelling. We eventually found an excellent brew suitable for trowelling and a continuous temperature rating of 1400 deg C. However it took some weeks to sort all this out and get the stuff and instructions delivered from interstate.

Casting of complete arches for small power locos, instead of using numerous bricks like in the SAR days is nothing new for the SHR – from memory we first started them in the late 1980s. An Rx arch would contain about 50 bricks which all had to be individually cast, then cemented together in the firebox to form the brick arch. While casting the arch is a solid 2 hour job, it would probably still take longer to build the arch from all the bricks let alone having to cast them one by one.

A steel former plate designed many years ago by Ron Williams with supporting timbers underneath for the new firebox arch was fitted.

The front edge of the arch is somewhat thicker than the one it replaced. This should provide a larger heatsink and maintain better firebox heat, particularly when the loco is standing at stations between movements.

There was a fairly long curing and preheating process required for the new arch. There is a preferred time of 48 hours before the former can be removed, then another 48 hours air drying followed by a prescribed heating cycle. The first part of the cycle uses a fan heater in the firebox then a small kindling fire on the grates. If any of this is undertaken too quickly, the still trapped moisture in the arch turns to steam and the arch can explode.

The photos below show the casting supported initially by the former plate and in its final cured state


   

621

The Mechanical Services Manager reported in early December 2012 that the loco is running well with new coal. Superheater elements had been tested, repaired and refitted along with other boiler equipment. The tender was rinsed and boiler cold water hydro and steam tests were performed with a boiler ticket issued for a further 12 months. Over Xmas and New Year the loco ran alternately with 621.

However from just after Xmas a number of problems decended upon us.

December 27th

Unfortunately one of 621’s elements failed during a warm up at Goolwa Depot. All was a routine warm up until a sound was noted from the funnel that should not have been present. Once everything was put away, closed and stabled the smoke box door was opened, the spark arrestors removed to see if the draft was coming from the blast pipe. This then confirmed a considerable leak from one of the superheater elements. The loco was removed from service to allow a volunteer to go into the firebox once things had cooled enough to establish which element has let go.

December 29th

621’s steam leak was finally fixed. The problem was not a leaky element (which was good news anyway) but a strong leak from a misaligned cover plate on the regulator pilot valve. There was no easy way of locating exactly where the leak was because nothing was leaking out. Using compressed air from 958, 621’s boiler was pressurised to 40 psi and the leak became very evident. However by then we had already partly dismantled the smokebox and removed the top plates over the regulator valves chasing the leak we could hear but not see.

The offending plate was correctly positioned with a new gasket, then the boiler given an “air hydro” to 80 psi with no leaks whatsoever. This was followed by refitting smokebox baffle plates, the funnel petticoat and spark arrestor screens plus the two outer regulator cover plates and a fire lit at 1210 hrs today.

December 30th

While we fixed the steam leak yesterday, this morning the engineman could not open 621’s regulator. It was initially suspected that corrosion has set in between the stainless balance piston (part of the regulator valve) and the cast iron bore it works in. This has happened before and it very effectively locks the valves up and on this occasion has occurred because the boiler has been sitting for too long (only a few days) without the condensate being flushed out with treated water and the fact fresh air has gained access via the bits removed while chasing the original steam leak. Again nothing can be done until boiler pressure is zero and things cool down sufficiently to work on

December 31st

It was found that with low or no boiler pressure the regulator worked OK except for some notchiness at the start and at the mid point. This was felt by hand on the pilot valve quite distinctly. This led to a new theory that the camshaft end float was excessive creating misalignment between the cam lobes and the spigots on the bottom of each valve .

At about the same time Ian Johnston noticed some interference between the bottom of 2 of the 3 main valve balance pistons and the camshaft underneath these – this certainly should not be the case. In a phone chat with volunteer Peter Brown he theorised that with 200 psi pressure bearing on top of the valve pushing it down onto the camshaft, it was very possible that rotation of the camshaft (opening the regulator) was almost impossible due to the forces involved. This theory fitted all symptoms and the reason for it is just wear and tear considering these components work in an environment of 200 psi superheated steam at around 400 deg C.

While header regulators (compared to dome regulators) have one good feature (after the elements and close to the cylinders for quite precise admittance of steam to the cylinders), they are quite complex requiring a myriad of fairly close tolerances and are hence prone to giving trouble and requiring lots of head scratching and maintenance. The valves and seats also are prone to getting nicks and dents in them resulting in unwanted regulator leaks. Over the years 621’s Log Book is riddled with entries on the regulator.


January 3rd

Work on the regulator continued as described by Ian Johnston in an email report that might give readers an insight into the complexity of the mechanism that our volunteers and small paid staff have to keep on top of, unseen by paying passengers and most ARHS members.

"As mentioned previously, 621’s regulator has provided a number of challenges over the years including ensuring it is reasonably steam tight. This is desirable when working daily CTs because the boiler retains more pressure and water overnight making the lightup next morning much easier. But the design of the valves and their respective narrow seats is that they are prone to getting small nicks and dents across them resulting in leaks! A small piece of scale inadvertently jammed on the valve seat will result in such a nick, with the scale more than likely coming from the inside of a superheater elements just before the regulator. (All sorts and sizes of bits of scale can be formed in elements mostly while the loco is idle). So this means all too frequently the seats and valves have to be cut and machined to get rid of the nicks etc, but you can only do this so often otherwise the valve ends up getting too low in the header and the operation of the regulator gets out of adjustment. This is what happened last Sunday when engineman Peter Brown could not open the regulator at all and had followed work on the seats and valves before 621 transferred to Goolwa Depot.

Already reported was the fact that 2 of the 3 valves had dropped to make contact with the operating camshaft underneath and this was then thought to be the sole reason for the stuck regulator. But further head scratching and measurements revealed that the lowered main valves had drastically reduced the amount of pilot valve lift before the cam lobes picked up No.1 valve and tried to open it. The normal lift is 8 mm but all we found Monday was 2 mm (1/4 of what it should be) which meant very little steam was able to flow via the pilot valve to provide the necessary balancing effect underneath No.1 valve so it could be opened easily against the 200 psi boiler pressure.

To overcome the camshaft contact issue, between 1 and 2 mm has been machined from the balance piston on each valve to ensure sufficient clearance. To increase the pilot valve lift, 3 mm has been machined from the base of each main valve where the cam lobes make contact, which means the pilot valve now lifts 5 mm, not the full 8 mm but it is hoped this will provide enough pressure to provide a sufficient balancing effect – only time will tell with 200 psi in the boiler to prove this one way or the other. While more could have been machined off, the 3 mm was a compromise between improving the current situation and hopefully having a working regulator to taking off too much and being sorry later.

The valves were machined at our Mount Barker Depot yesterday by fitter Shaun and this morning I fitted and fiddled with the valves then measured the valve lifts and all looked quite promising. However all fingers and toes will be crossed when the loco is expected to be lit up again – weather permitting. If the regulator is OK at 200 psi, then 621 will finally be back in service. Sometime before June 2013 the whole regulator assembly will have to be seriously worked on and brought back to drawing specs. The above work is to hopefully have it operating up to then."

[IMAGE] 621 - Major Rehabilitation 2007 / 2008

Then Loco Manager Ian Johnston has compiled a detailed list of tasks undertaken in 2007 /2008 on tasks leading up to the loco test runs and the its return to service on the 17th August after a lengthy period of maintenance. Click  HERE  to download Ian's report (in PDF format)

A small number of tasks were attributable to damage incurred in a minor derailment near Gemmells; a bent draw bar, broken speed recording sender unit and some minor dings to wheel rims and brake rod supports under the tender. All other work performed was due to normal wear and tear along with the age of our equipment requiring some routine heavy maintenance.

The description of the tasks does not indicate the time spent which can vary from a few hours to a number of weeks. Hopefully the list will give "non mechanical" volunteers some appreciation of the scope of the work we undertake with very limited resources and why the maintenance of such "old" machines, which includes everything we operate, is a large task fraught with difficulties due to the age and condition of many bits and pieces.

The loco returned to service by operating trains from Mt Barker to Victor and Strathalbyn on Sunday August 17th 2008 This was a success and we now plan to use the loco to run the Southern Encounter and Cockle Train on the first and third Sundays until late November, the October School Holiday Cockle Trains and the Highlander to Strathalbyn on the second Sunday of September and November.


[IMAGE]A Rust Problem - September 2008

The loco team were looking forward to a busy fortnight of steam Cockle Train running when they lit up the loco on Saturday 27th September in preparation for taking it to Goolwa Depot. However the dark clouds descended when it was obvious there was a serious steam leak from the regulator and no more than 10psi could be raised!

Here are some words from Ian Johnston on what then eventuated.

"We have had some rotten luck with 621 today (Saturday 27th Sept) during its preparation to transfer to GD for the forthcoming CTs. Once boiler pressure began to rise, a significant steam leak from the regulator (via the release cocks) became very obvious to such an extent that from 10 psi, no more pressure would accumulate easily due to the leak. A number of "tests" were undertaken to try and work out what the problem might be but nothing at all showed up.

Ron Williams and I delved into 621's regulator first thing on Sunday morning and found a good reason for the heavy steam leak - No. 3 valve was stuck open at least 1/16 inch. Doesn't sound much but on a 3 inch diam valve, it leaves an awfully big gap. The reason for this appears to be our old enemy - a slow build up of a small amount of galvanic corrosion around the balancing piston, mostly on No.3 valve because it is the last one to sequentially open and hence does not open very often during normal running.

Some more pertinent info revealed itself on Monday morning when the superheater header had cooled down. The bottom chamber of the header is what is called a balancing chamber which is in communication with steam once the regulator has been opened but steam only flows to it (not through it) to apply an equal steam pressure to the underside of the valves to "balance" them so that very little physical effort is required to open them against the boiler pressure

We found a significant amount of corrosion products accumulated in this bottom chamber, so much so that under No. 3 valve, the pile of rust and scale made contact with the base of the regulator valve and prevented it from seating fully.

The amount of corrosion around the balancing piston and its bore was minimal and I was curious how this alone might have impeded the valve closing. The reason for this large amount of rubbish could well be linked to the fact that for 3 months the boiler sat completely idle full of treated water and that the pH in the header could not be monitored and adjusted as could the boiler water itself. So during that 3 months a significant amount of corrosion would have taken place as nature dropped the pH for us. What we will need to do in the future is monitor the corrosion process inside the header on a fairly regular basis until we are satisfied as to what has just happened was more of a one off due to the 3 months of wet storage."

Attached is Ian's photo of about two mugs full of corrosion products found in 621's header although the height of the pile does not show all that well. This stuff, representing about 90% of the total, was removed from the bottom balancing chamber of the header with most of it piled up under the No. 3 regulator valve, this being the prime reason for impeding the closure of that valve and hence the problem last Saturday.

The loco was steamed up again on Tuesday morning and ran light engine to Goolwa where it took over from DE507 to run the final Cockle Train of the day.


[IMAGE]And then another problem during the October Running

On stabling the loco at Mt Barker after a very busy and fruitful SE/CT day on the 5th October , the customary listen in the firebox revealed an ominous loud hissing noise, usually associated with a cracked/broken crown stay or a leaky element. It turned out to be the former but instead of the "normal" slow bubbling of steam and water from the stay telltale (leakage) hole, it was running water. This indicated the stay was well and truly broken and because of the amount of water flowing into the firebox, it was impossible to determine if any other suspect stays might have been contributing. Consultation with the boiler inspector confirmed 621 was a no go until the extent of the leak had been investigated and if relatively minor, the leak could be temporaily plugged.

The stay was plugged once the loco had cooled down, but still in a hot but bearable environment with a simple tapered steel plug hammered home hard. This normally works as a temporary stop gap until a window presents itself to remove the broken stay and replace it with a new one. Among all the thousands of stays around 621's firebox, there are 3 rows of 24 flexible crown stays on each side of the firebox (144 total) located along the radius of the inner firebox in the transition from the flat crown sheet to the vertical sides. These stays carry most of the load when the firebox is at its hottest and hence fully expanded. Unfortunately these stays are fairly old - most date back to the 1950s and hence are prone to cracking and sometimes breaking. Once this has happened it is desirable to replace the stay as soon as practicable so as not to overload adjacent stays resulting in the same fate. And if any two adjacent stays play up, it is instant withdrawal of the boiler - and hence the loco. We have previously operated for short periods with one stay plugged and this is acceptable provided frequent monitoring of the situation is maintained - again for obvious reasons.

Ian Johnston's photos shows the results of the leak first up and then the same thing after a bit of a clean up and the plug hammered into the tell tale hole. We will be closely watching that this plug remains in place and no other stays start to leak. The reason the stay head immediately to the left of the crook stay looks different is that it is an earlier replacement stay and rather than rivet the heads over, we now run a fillet seal weld around the head - much quicker, easier and safer than using a rivet gun in a confined space. The 3 blobs across the top of the photo are the "button head" ends of the crown sheet stays - a different type of stay but does the same thing.

The loco was returned to Goolwa to resume duties after a break of just a couple of days.


[IMAGE]Much Bigger Problems - December 2008

The Initial Assessment

(18th December 2008)

Our hardworking Mechanical Services team had a Christmas present that they did not deserve when routine inspection of the loco in preparation for summer Cockle Train workings revealed water in the smoke box which was traced to an 8mm crack in one of the 20 year old flue tubes.

It was initially thought this could be welded up but removal of the flue confirmed a much more serious and major problem, which resulted in the boiler inspector condemning all flues and boiler tubes. This will unfortunately mean 621 will not be available over summer, and we will have to rely on DE507 and railcars

Apart from an indicative cost of around $50000 for new flues and tubes alone, procurement of material and consequent fitting will be a massive task taking into account our limited resources and based on previous experience other unpredictable maintenance work inside the boiler could well be required.

Here are a few more details at this early stage

  • Removal of the flue revealed a stress corrosion problem in the end of the flue tube, hence the crack, hence the leak. Based on the age of the flues, it is believed the metal has crystallised and because of that and the thinness of the flue walls plus a few other factors, BD has had no hesitation in condemning all flues - no good even for reuse as they have been in the boiler for 23 years and are already second hand. Then based on all of the above, the same reasoning has been applied to the tubes. So to cut a long story short, all flues and tubes require replacement; not suprising - they have had an extremely long life.

  • We have 16 flues purchased for 520 in 1994 which can be used in 621. We will need to purchase a minimum of 6 new flues. We have no spare tubes and will need to purchase over 100

  • We hope to have a more accurate view as to where we are heafing within a couple of weeks so watch these pages, and if anyone feels they wish to contribute financially or in any other way to this unexpected setback - please contact us.

  • Obviously work on retyring Rx207 will be put back for the moment - speeding up this work rather than putting resources onto 621 was considered by BOM but was not a realistic option.


Work Assessment

16th January 2009

Since November deciding in requirement to replace all 22 flues and 102 boiler tubes, a reasonable amount of physical work has been undertaken and seemingly an equivalent amount of time spent on measurements and calculations to determine the exact state of the firebox and smokebox tubeplates, both 50 years old having been fitted as part of the last general boiler overhaul by the SAR in 1959. The main activities were;

  • all flues (5 1/2 ins. diam) were removed first and this has never been an easy task. First the welded flue ends were tediously ground from the firebox tubeplate then the expanded flue ends in the smokebox slit with an oxy torch and partially collapsed to release that joint. This was followed by the hardest part, slogging the firebox end of the flue with a sledge hammer while cramped in the firebox until that expanded joint released itself and the flue moved forward about 100 mm.

  • with the each flue released, a shackle was attached to the smokebox end of the flue and the hydraulics of the Leyland truck used to drag the flue from the boiler. It was then a task for at least 3 chaps to transfer the flue to the tray of the Leyland - the flues are that heavy.

  • the removal of the 102 tubes (2 1/4 ins. diam) required the same process, except the hydraulics, and was easier due to their much smaller size.

  • the condition of all flues and tubes was fairly good corrosion wise but together with their by now relatively thin walls and age , the boiler inspector considered their use by date was up.

  • with all flues and tubes out, it was time to clean the scale from the interior surfaces of the boiler including the barrel sides, tubeplates, feed water tray, palm stays, internal pipes etc. Although the interior was considered to be reasonably clean, a number of buckets of scale resulting from many years of water boiling, were removed. What was very heartening was the effective layer of iron tannate deposited on all surfaces from the tannin treatment to the boiler water. The tannin also assists in removing scale and sludge via the blowdown valve.

    Ian's photo caught young volunteer Oliver Lukins hard at work descaling the boiler.

  • a few weeks was then spent grinding excess weld from the tubeplates, cleaning and deburring all flue and tube holes and cleaning the water side of both tubeplates (required needlegunning as well) - all these tasks being pretty dirty affairs.

  • at this stage the "bible" of pressure vessels, Australian Standard 1210, was being consulted and calculations started to determine how the tubeplates measured up against the AS with regards to the specified pitch of all holes, minimum ligament widths between holes, maximum permitted hole diameters and tubeplate thickness.

  • a number of sets of AS based calculations were carried out to see how the tubeplates compared with their original drawings, tolerances permitted by the AS, the current tubeplate thickness and hole diameters and finally the repair options proposed by ourselves.


    Fitter
    Ron Williams
    accurately
    measuring the
    smokebox
    tubeplate

    Photo:
    Ian Johnston


  • the calculations showed the condition of the firebox tubeplate was such that it could probably be used without any major work required on the plate itself but that the diameters of the swaged ends of both the flues and tubes would need to be increased to allow for the increased diameter of all holes.

  • the same calculations applied to the smokebox tubeplate showed that the plate required some major work or even partial replacement. The main deficiencies were related to oversize and oval flue holes resulting in undersize ligaments plus oversize tube holes although the ligament widths were still acceptable. After much discussion, our final proposal was to reform the flue holes by welding followed by machining back to drawing size and to "bell" out the ends of the tubes to more closely match their respective holes. This is much more preferable than over expanding tubes out to the oversize holes. The AS allows holes to be no more than 0.100 ins. larger than its corresponding flue or tube and that is one of the limits we have to work within.

  • a meeting was held at Mt Barker on 14/01/09 with our boiler inspector, Bernie Dickinson, and SteamRanger's Ron Williams, Ian Johnston, Bob Sexton and a number of interested volunteers to discuss all aspects, calculations, current corrosion wastage of tubeplates (minimal at about 0.060 ins.) and our proposed repair methods. Bernie confirmed our calculations and interpretations of AS 1210 to be correct and endorsed the welding repairs to the smokebox flue holes. The holes will be machined after making mods to our magnetic based drill to adapt it to use more as a borer.

  • however before any of this takes place, there are two more critical and major determinations to be carried out on both tubeplates - magnetic particle tests for cracks in holes and ligaments on both sides and ultra sonic testing of the thickness of the entire plates to ensure their compliance with the AS. Until the plates pass these tests we cannot conclusively say that either plate is still suitable for use. So for the next week or two, the outside faces of each tubeplate need to be cleaned back to bare metal followed by the crack testing of both sides of both plates then if no major issues arise from that, ultrasonic thickness testing of both plates. If at this stage both plates can be used, albeit with a fair bit of welding and machining on the smokebox plate, new flues and tubes can be ordered with some hunting around for someone to swage and bell the ends of both as required.



The photos above speak for themselves. The close up of the water sides of both plates (smokebox (L) and firebox (R) )shows the degree of cleaning required for crack testing - back to bare metal. It also gives some idea of the spot corrosion on the plates - in most cases looks worse than it is.  


Latest News - 7th February 2009



There is not a lot to see visually (except for the crack testing white paint) as to what has gone on with 621 tubeplates since the 14 January report but there have been a fair amount of time consuming tests and some repair work started.


  • Ron Williams spent a few days undertaking the magnetic particle crack testing of both sides of both tubeplates including the flue and tube seats in each hole. Both tubeplates showed minor but fixable cracks, the most significant being a "shower" of surface cracks on the water side radius between the very bottom tube hole of the smokebox tubeplate and the barrel. It is intended to grind the cracks until they have completely disappeared (as indicated by MP testing) then build up the plate with pad welding - a slow process to prevent any undue heat stresses being set up. A few tube holes in both plates have small radial cracks which will be similarly ground out and welded.

  • Boiler Inspector Bernie Dickinson has kindly loaned us his ultra sonic thickness meter to measure the tubeplates' thicknesses at dozens of spots. The probe requires perfectly flat and smooth surfaces to yield accurate results so many spots were prepared on both plates and these correspond to the numbers seen on this photo. While there is some thickness wastage of both plates, a bit more than we had theorised, Bernie considers that there is still adequate thickness in both plates.



  • Some time has been spent in developing and perfecting techniques to weld all smokebox tubeplate flue holes due to their being oval in shape and oversize, plus four tube holes with the same problems. As a means of providing a full and clean weld edge on the back (water side) of the tubeplates, a number of firebrick "pavers", as used in slow combustion heaters, were purchased. These will be clamped to the water side of the tubeplate with the welding rod being run against the paver from the smokebox side. A "flue hole" was cut into a vertically mounted steel plate on the bench and our magnetic base drill was adapted to run a cutting tool to machine the hole, before and after a welding run had been applied. After some fine tuning by Ron Williams, this technique has worked a treat and provides a very easy and cheap way of reforming the holes.

  • As well as the above hole repairs, two tube holes in the firebox tubeplate and ten in the smokebox tubeplate have ovalities exceeding 0.040" - one at 0.086". The higher the ovality, the more difficult it becomes to expand a round tube into an oval hole using a circular expander. Previous experience in SR and elsewhere has shown the holes with ovalities over 0.040" can be leakers on the first (and subsequent!) hydros. The two firebox tube holes have already been bored using the magnetic base drill set up as a borer.

  • All the holes (22 flue, 10 tube) to be welded have been "centred" and "circled" so that when the cutting tool is set up to machine the welded holes, the scribed circle, based on plotting the hole centre, around each hole is used to centralise the cutting tool. Don't need a newly machined hole to be offset from its centre.

  • Calculations and measurements showed that most tubeplate minimum ligament widths satisfied AS 1210 except for a few around the flue holes in the smokebox tubeplate. However the repair work on those holes effectively makes them smaller thus increasing the ligaments to acceptable widths.

  • The question of swaging and belling of the new flues and tubes as required is being actively pursued but not with a lot of luck at this stage. Ideally it would be nice if this work could be done in Adelaide but a number of firms we have approached either are not set up to do it or don't want to do it. There are firms capable of the work interstate but it will be a costly exercise to transport flues and tubes across the border and back. The firebox end of the flues and tubes need to be swaged down in diameter while the smokebox end of the tubes need to be belled up in diameter - all to non standard sizes because of the necessity to have all flues and tubes as close as possible to their respective existing hole diameters.

  • A 16 page report has been drafted covering all aspects so far; what we found, what was considered to be why, options of replacement or repair, loads of calculations as required by AS 1210, final repair proposals and why, and the boiler inspector's endorsement of everything being proposed.

  • So far so good for the existing tubeplates but the writing is certainly on the wall that both plates will more than likely need to be renewed at the next major internal inspection, maybe 10 years time.

    January 2011 Update

    In early January David Groves completed tack welding the two halves of 621's new combustion chamber plates into position ready for the full welding process. Once fitted, our contractors RCR can access the firebox to start their work in early February including machining the flue holes in the smokebox tubeplate then fitting the new tubes and flues . After their work, over 100 flexible stays will need to be machined and fitted - an awesome sounding task.

    Here's a photo of David's handy work so far. The shots show the entire section that is being replaced. The plate is being installed in two sections due to the size and weight of the plate and poor access for the plate in one section.

    David has cut the old (original 1936) wasted section out using an angle grinder as opposed to oxy making it a rather neat cut. The view shows the entire section made up of two separate sections that will obviously meet with a weld in the middle. Installation of the first section was a rather straight forward task given the size of the hole it is fitted into. The second section proved a little more difficult as the pate is being installed from the inner side of the radius rather than from the outer, thus requiring a fair bit of grinding in order for the plate to fit into its hole but without relieving the gap to much and making the plate too small. All sounds easy however in practice it required a number of hours to get it correct first time.

    Added to the difficulties of installing the new plate is the many corners of previously replaced sections from the SAR days. It does not appear they were quite so fussy with ensuring the sections of plate were flush with the section it was being butted to. This required much dogging and manipulation of the new and old plate to create the best match. AS can be seen the plates are currently tacked in place ready for David to spend a number or hours preheating and welding the sections in. This being a rather delicate task as the combustion chamber section removed gives support to the firebox tube plate. David has provided a number of makeshift longitudinal stays between the firebox and smoke box tube plates to ensure the firebox tube plate does not move at all throughout the process. These stay were made up from some of the old tubes that were removed. Yet to be removed is another smaller section of plate immediately to the rear and centre of the current sections being replaced and taking in the replacement of another 7 flexible stays.

    The ship carrying our container of flues and tubes for 621 and Rx224 arrived in Adelaide in mid January with our cargo delivered to Mt Barker soon after. Cleaning and annealing the ends of the 200 tubes and 22 flues will be carried out by SteamRanger personnel with RCR Energy Services scheduled to start work on boring the smoke box tube plate holes in the first week of February. This task is expected to take six or seven days. After this time installation of the flues and tubes will also be carried by RCR with appropriate hydrostatic boiler tests to take place once the boiler is ready.




April 2010


An important series of firebox thickness measurements has just been completed and the results are not quite what we wanted. These measurements were started last year but did not progress very far due to the loco being "mothballed", then the 15 year old borrowed thickness meter went on the blink which resulted in a 3 month repair job including new parts having to be sourced from the UK. Prior to this the meter did perform faultlessly measuring the thicknesses of both of 621's tubeplates. After the repair work the meter was "borrowed back" and was used on the firebox of the paddlesteamer "Marion" and from all accounts they obtained satisfactory results. However shortly after when we again restarted work on 621, the meter would calibrate OK but would stay locked on that reading and not take any measurements so it is now back with the repairer. It would be nice to have our own meter, and one day perhaps we should, but they are not cheap at a couple of thousand $s a piece. Not wanting to lose another 3 months, last week we were fortunate to be able to borrow another more modern meter. Ultra sonic meters such as these depend on clean, polished and flat test spots and none of these normally exist in a firebox. This meant almost 500 spots had to be prepared using a polishing disc - a tedious, dirty and time consuming task, more so when there is a fair degree of surface pitting. Some of these prepared spots can be seen in Ian's photo.

Earlier measurements along the firebox side plates indicated some expected wastage in the plate thicknesses but not enough to be an issue. However measurements taken in late April in the combustion chamber (CC) indicated the plate thickness along the bottom of the CC (at 6 o'clock) was down to condemning level. The CC forms the forward section of the firebox and can be seen in the photos as the chalked section just behind the tubeplate. The chalk lines indicate the welded plates of the CC but it is only the lower one third of the CC which is in question (roughly corresponding to the hatched section). Whether we replace the whole chalked section or only part of it has yet to be decided with our boiler inspector. We need to determine whether we need to replace the hatched section of the inner throatplate which also has some wastage. The brick arch is normally located at the edge of the hatched section back towards the camera.

While we have replated fireboxes in the past, notably Rx 207's, we have not carried a repair of this size. The cutting, rolling and welding of new plates is fairly routine but the lining up, drilling and tapping of around 100 stay holes will be a challenge. With the current lead time on the acquisition of new tubes and flues, unless some more unknown nasties pop up, it is not expected that this repair work will seriously delay overall progress on 621.

Why is it then that only the bottom of the CC is currently a problem and the rest of the firebox, based on the measurements taken, is acceptable? Probably a couple of reasons. The first is found in the boiler's records which show 621's boiler was overhauled in 1941, 1948 and 1959. In the first two overhauls a number of repairs and patches were applied to all firebox plates except the CC which appears to have survived without giving much trouble (being protected by the brick arch from spiky thermal stresses, cold air etc would be one reason). In 1959 both the tubeplate and crown sheet were completely renewed so the records suggest that the CC is original from 1936 - not bad going. The second reason is that it is a well known fact that the underside surfaces of any part of a boiler, including tubes and flues, suffer from more corrosion due to many friendly bubbles of air being trapped on those surfaces, particularly when a boiler cools down and what is worse, the bubbles can stay there. So the combined presence of steel, air bubbles and water is a great scenario for corrosion.


September 2010

There has been a lot of investigative work carried out of this loco in order to provide a scope of work required to return the loco to service. This has also included 4 months of negotiations with tube suppliers and a possible private donor to fund the boiler works. It is with great pleasure that I can now report to the membership that negotiations with a private donor have been successful in obtaining the funds for the boiler work in order to return 621 back to active service. The donor has provided funding for the purchase of flues and tubes to order immediately ex Willingale Tube Manipulation and Fabrication U.K., Britain's largest boiler tube supplier.

Tubes are being manufactured in Germany and manipulation (swaging and belling of the ends) carried out by Wilingale then shipped to Adelaide. Further funding by the donor is being provided to outsource the boiler works (boring of tube plate and tube installation) to RCR Energy Services (AKA Tomlinson Boilers). Supply and shipping of all materials for this work will take 6 months and is expected to land in Adelaide sometime in December. You may recall the comparison of cost from a local supply in Australia as opposed to overseas supply was a saving of almost half the cost including shipping.

On a private trip to the UK Ian Johnston took the opportunity on 9th September to visit Willingales in Suffolk, UK, who are the suppliers of flues and tubes for 621 and 224. They have a large setup for doing all sorts of things to all sorts of tubes and are one of the last firms in the UK to be able to handle any sort of task. The swaging and belling of 621 boiler tubes has been completed. The internals of their hydraulically powered swager is shown in this photo (such a machine would be very handy at MB). 621's flues and 224's odd 1 7/8" diameter tubes had at that stage not been delivered from Germany. Still amazing that all this procurement, swaging, belling and transport can be undertaken from the UK much cheaper than through Aussie suppliers. However by comparison there is quite a large market in the UK and Europe and Willingales export all over the world. To them ours is quite a small order.

Back at Mt Barker separate work has been performed throughout the firebox with extensive thickness testing being carried out of all surfaces showing up some areas requiring minor repairs to the side plates. A not so good area is the lower radius section of the firebox combustion chamber showing thickness has reached it condemning level. Repairs will require a reasonably large section of the combustion chamber to be cut out and renewed also requiring the replacement of somewhere near 100 flexible ball stays. This task is not beyond the capabilities of our own volunteers and is not expected to delay the project as this repair can be carried out concurrently with other boiler work.

Previously reported activities

  • Boiler     It is with great pleasure that we can now report that negotiations with a private donor have been successful in obtaining the funds for the boiler work. This has allowed orders for purchase of flues and tubes from Willingale Tube Manipulation and Fabrication U.K. Tubes have been manufactured in Germany and swaging and belling of the ends will be carried out by Willingale. Further funding by the donor is being provided to outsource the boiler works (boring of tube plate and tube installation) to RCR Energy Services (AKA Tomlinson Boilers) in SA.

    Supply and shipping of all materials for this work is taking some 6 months and delivery is expected in Adelaide sometime in December 2010. You may recall the comparison of cost from a local supply in Australia as opposed to overseas supply was a saving of almost half the cost including shipping.

    SHR volunteers will be aware that longserving mechanical services "guru" Ian Johnston has recently been on holiday in the "Old Dart", during which he took the opportunity to visit Wellingales in Suffolk, who are the suppliers of flues and tubes for 621 and 224.

    They have a large setup for doing all sorts of things to all sorts of tubes and are one of the last firms in the UK to be able to handle any sort of task. The swaging and belling of 621 boiler tubes have been completed and are seen as 5 bundles in this photo. 621's flues and 224's tubes had not been delivered from Germany when Ian visited.




  • Firebox     Separate work has been performed throughout the firebox with extensive thickness testing being carried out of all surfaces showing up some areas requiring minor repairs to the side plates. A not so good area is the lower radius section of the firebox combustion chamber showing thickness has reached it condemning level. Repairs will require a reasonably large section of the combustion chamber to be cut out and renewed also requiring the replacement of somewhere near 100 flexible ball stays. This task is not beyond the capabilities of our own volunteers and is not expected to delay the project as this repair can be carried out concurrently with other boiler work.

    And here is a selection of Ian Johnston and Andrew Gramp's photos of some of the work in progress in early November

           
       

Negotiations with 621's donor have been successful in obtaining funding for the purchase of a complete set of 1 7/8 inch fire tubes for Rx224 of which will be manufactured and shipped with materials for 621. 1 7/8 inch tubes are no longer able to be procured in Australia.

January 2011

In early January David Groves completed tack welding the two halves of 621's new combustion chamber plates into position ready for the full welding process. Once fitted, our contractors RCR can access the firebox to start their work in early February including machining the flue holes in the smokebox tubeplate then fitting the new tubes and flues . After their work, over 100 flexible stays will need to be machined and fitted - an awesome sounding task.

Here's a photo of David's handy work so far. The shots show the entire section that is being replaced. The plate is being installed in two sections due to the size and weight of the plate and poor access for the plate in one section.

David has cut the old (original 1936) wasted section out using an angle grinder as opposed to oxy making it a rather neat cut. The view shows the entire section made up of two separate sections that will obviously meet with a weld in the middle. Installation of the first section was a rather straight forward task given the size of the hole it is fitted into. The second section proved a little more difficult as the pate is being installed from the inner side of the radius rather than from the outer, thus requiring a fair bit of grinding in order for the plate to fit into its hole but without relieving the gap to much and making the plate too small. All sounds easy however in practice it required a number of hours to get it correct first time.

Added to the difficulties of installing the new plate is the many corners of previously replaced sections from the SAR days. It does not appear they were quite so fussy with ensuring the sections of plate were flush with the section it was being butted to. This required much dogging and manipulation of the new and old plate to create the best match. AS can be seen the plates are currently tacked in place ready for David to spend a number or hours preheating and welding the sections in. This being a rather delicate task as the combustion chamber section removed gives support to the firebox tube plate. David has provided a number of makeshift longitudinal stays between the firebox and smoke box tube plates to ensure the firebox tube plate does not move at all throughout the process. These stay were made up from some of the old tubes that were removed. Yet to be removed is another smaller section of plate immediately to the rear and centre of the current sections being replaced and taking in the replacement of another 7 flexible stays.

The ship carrying our container of flues and tubes for 621 and Rx224 arrived in Adelaide in mid January with our cargo delivered to Mt Barker soon after. Cleaning and annealing the ends of the 200 tubes and 22 flues will be carried out by SteamRanger personnel with RCR Energy Services scheduled to start work on boring the smoke box tube plate holes in the first week of February. This task is expected to take six or seven days. After this time installation of the flues and tubes will also be carried by RCR with appropriate hydrostatic boiler tests to take place once the boiler is ready. The final step in 621's restoration was a test run to Goolwa depot and return on Sunday August 21st hauling steel car 710 and DE loco 958. The trip was a success with the boiler steaming excellently, as would be expected with an all new heating surface of tubes and flues. With the exception of one oil feed pipe to the driver’s side piston rod coming loose and the fireman’s side trailing truck axle box running rather warm all else ran like a Swiss watch. Tied in with some very crisp stack talk produced by the baker valve gear, there were smiles as far as the eye could see.

621 has subsequently hauled the regularly scheduled Southern Encounter and Highlander commencing on Sunday August 28th and will continue as train loco right through to the end of November, fire restrictions permitting.

For the record, final workshop milestones were:

  • Work on loco 621 previously went very much to schedule in July and August. The majority of the few remaining tasks were completed with little or no trouble or delay and as a result of a couple of marathon Saturdays where work went late into the evenings. We thank key players Craig Dunstan, David Groves and Shaun Cassidy for their assistance supported by other members of our volunteer mechnical services team. Installation of all 108 flexible stays and three flexible stay cups as manufactured by Dinki Di Engineering. The photo at the end of this report shows David inside the firebox combustion chamber seal welding the stays on the fire side.

  • On Saturday July 2 the first cold water boiler hydro test to 100 psi marked the first filling of the boiler since November 2008. With all flues and tubes holding pressure at 100psi and with the boiler then drained, welding of all flues and tubes in the fire box and appropriate stay tubes in the smoke box was performed as per current day standards. This task required approximately seven full days welding to complete. Once the welding was complete a further 100psi hydro test ensured any tubes upset during the welding process were “nipped up” by post welding expanding as required.

  • On Saturday 30th July, again another long day by many, the boiler barrel was washed out in preparation for a hot water hydro test to 250psi, being 1¼ times normal operating pressure and at a temperature of 60ºC. A number of tasks are required to set up the boiler for the hot water hydro testing. These include the addition of some external “bush” plumbing to connect the circulating pump to move water around from the rear of the boiler to the front to obtain the correct temperature mix throughout the entire boiler, along with plumbing for the hydro test pump to raise the required pressure.

  • In late July the first fire was lit in 621’s firebox in three years (top photo) marking a memorable moment for the monumental task undertaken and in mid August the fireman’s side conrod that was bent during the accident in 2008 and repaired by contractors HeavyMech, looking much straighter now, will be installed with the remaining rods. The boiler was then scheduled to undergo a full steam test with a test run to follow a week or so later.




March 2011

In early March contractors RCR started the boring process of machining a total of 14 tube holes and the 22 flue holes in 621's smokebox tubeplate, good timing having just dispatched 207 to GD. The setting up and boring of the first tube hole has been an all day task due to RCR's chaps (Clinton and Patrick) coming to grips with this sort of task and the boring machine they have hired for the job. The machine does a good job but has some limitations due to its size (see photo) with difficult access to the hole being bored, mainly to take diameter measurements to keep tabs on the bore. However once a couple of holes have been completed, it is hoped a technique can be developed to speed the process up a bit. The flue holes won't be so difficult due to their larger diameter - 142 mm compared to 61 mm. Have to talk metric to the RCR lads as that is all they work with. We had to obtain a DCMB/CFS permit to operate our mini forge to anneal both ends of all tubes and flues before expanding into the tubeplates. Just like Phil N has found out down south, getting these permits nowadays is like extracting teeth from intractable boffins.

Another one of those milestones we like to see, this time all of 621's 102 boiler tubes are in their respective holes in the boiler tubeplates although not fully expanded as yet. A few week's work beforehand was undertaken to anneal both ends of each tube by using our purpose built forge to heat the ends to cherry red then clean and polish the ends back to bare metal. (Our first photo below shows new volunteer Chris Lings cutting his teeth on the forge with the draught being supplied by 621's lightup blower). As usual there have been some hic cups which can be summarised as follows;

  • in an endeavour to save a fair amount of money, the firebox end of all tubes were swaged to a diameter which just fitted the smallest diameter tube hole in the firebox tubeplate. One of the big drawbacks of retubing a boiler with old tubeplates is that tube and flue hole diameters are all over the place due to wear and tear of a number of previous retube jobs. As our tube holes are now oversize (but most not excessively) and non standard, special swaging dies had to be made at close to $2000 a set - just for one diameter, so that's why there is only the one swage diameter.. One of the issues with 621's tubeplates has been the many varied diameters of the holes and as most would recall, the smokebox flue holes being excessively oversize, had to be welded up and machined to drawing diameter.

  • at the firebox end it was found too many new tubes were protruding into the firebox too far, around 15 mm instead of about 8 mm due to too many of the holes being too large. The result of this was too much of the swaged tube protruding into the firebox and too little protruding into the smokebox. This effect was predicted but not to the extent it has happened and it has resulted in the tubes bottoming out on the water side of the tubeplate at the top of the swage radius instead of near the bottom of that radius. The consequence of this was that those tubes cannot be properly anchored onto the tubeplate by the radius and the tube expansion/fillet seal weld between the tube and tubeplate on the fire side.

  • as this was predicted but not quite on the scale it has occurred, the fall back plan was to prosser roll the tubes after their initial expansion into the tubeplate. Prosser rolling is undertaken with specially shaped rollers (bit like a small dumbbell) so that the larger diameter ends of these rollers slightly flare the open end of the tube in the firebox and slightly expand the tube a couple of mm past the tubeplate on the water side resulting in a slight bulge which acts to anchor the tube to the tubeplate on the water side. In effect this bulge replaces what should have been a healthy swage radius and is an acceptable boiler practice. Hope all that makes sense!

  • A trial fitting of two tubes was undertaken on Monday 4/04/11 with a normal expansion followed by the prosser rolling and both procedures worked like a charm. So a lot of physical work saw all remaining 100 tubes slotted into the boiler. The RCR Energy chaps are now in the process of a two stage expansion procedure of all tubes in the firebox followed by the prosser rolling. Two stages are best as the first stage to about half expansion provides support for the tubeplate ligaments between all holes before the tubeplate is subject to heavier forces during the final expansion - prevents any possible distortion of the now well used tubeplates. Then the tubes will require the same two stage expansion in the smokebox but not the prosser rolling.

  • In the meantime, work has also been undertaken on the 22 new flues. As received these were covered by a tenuous protective coating which has taken some elbow grease and kero followed by steam cleaning to remove it - not the sort of stuff we need in a boiler trying to make clean steam. The task took longer than it should have with a dysfunctional steam cleaner having long moments of laying down and only providing cold water - no steam!! There could be some difficulties with the fitting of the flues into the rebored holes in the smokebox tubeplate which are now to drawing size. So are the new flues meaning there is not much clearance between the tubes and holes. But it has only just been discovered that for some reason some flues are oval by 0.040" or 1 mm - not much but enough to make them a tight squeeze across the wide diameter. The cleaned flues are currently being annealed then the ends will need the same cleaning and polishing as the tubes.
   




In early March contractors RCR started the boring process of machining a total of 14 tube holes and the 22 flue holes in 621's smokebox tubeplate, good timing having just dispatched 207 to GD. The setting up and boring of the first tube hole has been an all day task due to RCR's chaps (Clinton and Patrick) coming to grips with this sort of task and the boring machine they have hired for the job. The machine does a good job but has some limitations due to its size (see photo) with difficult access to the hole being bored, mainly to take diameter measurements to keep tabs on the bore. However once a couple of holes have been completed, it is hoped a technique can be developed to speed the process up a bit. The flue holes won't be so difficult due to their larger diameter - 142 mm compared to 61 mm. Have to talk metric to the RCR lads as that is all they work with. We had to obtain a DCMB/CFS permit to operate our mini forge to anneal both ends of all tubes and flues before expanding into the tubeplates. Just like Phil N has found out down south, getting these permits nowadays is like extracting teeth from intractable boffins.

Another one of those milestones we like to see, this time all of 621's 102 boiler tubes are in their respective holes in the boiler tubeplates although not fully expanded as yet. A few week's work beforehand was undertaken to anneal both ends of each tube by using our purpose built forge to heat the ends to cherry red then clean and polish the ends back to bare metal. (Our first photo below shows new volunteer Chris Lings cutting his teeth on the forge with the draught being supplied by 621's lightup blower). As usual there have been some hic cups which can be summarised as follows;

  • in an endeavour to save a fair amount of money, the firebox end of all tubes were swaged to a diameter which just fitted the smallest diameter tube hole in the firebox tubeplate. One of the big drawbacks of retubing a boiler with old tubeplates is that tube and flue hole diameters are all over the place due to wear and tear of a number of previous retube jobs. As our tube holes are now oversize (but most not excessively) and non standard, special swaging dies had to be made at close to $2000 a set - just for one diameter, so that's why there is only the one swage diameter.. One of the issues with 621's tubeplates has been the many varied diameters of the holes and as most would recall, the smokebox flue holes being excessively oversize, had to be welded up and machined to drawing diameter.

  • at the firebox end it was found too many new tubes were protruding into the firebox too far, around 15 mm instead of about 8 mm due to too many of the holes being too large. The result of this was too much of the swaged tube protruding into the firebox and too little protruding into the smokebox. This effect was predicted but not to the extent it has happened and it has resulted in the tubes bottoming out on the water side of the tubeplate at the top of the swage radius instead of near the bottom of that radius. The consequence of this was that those tubes cannot be properly anchored onto the tubeplate by the radius and the tube expansion/fillet seal weld between the tube and tubeplate on the fire side.

  • as this was predicted but not quite on the scale it has occurred, the fall back plan was to prosser roll the tubes after their initial expansion into the tubeplate. Prosser rolling is undertaken with specially shaped rollers (bit like a small dumbbell) so that the larger diameter ends of these rollers slightly flare the open end of the tube in the firebox and slightly expand the tube a couple of mm past the tubeplate on the water side resulting in a slight bulge which acts to anchor the tube to the tubeplate on the water side. In effect this bulge replaces what should have been a healthy swage radius and is an acceptable boiler practice. Hope all that makes sense!

  • A trial fitting of two tubes was undertaken on Monday 4/04/11 with a normal expansion followed by the prosser rolling and both procedures worked like a charm. So a lot of physical work saw all remaining 100 tubes slotted into the boiler. The RCR Energy chaps are now in the process of a two stage expansion procedure of all tubes in the firebox followed by the prosser rolling. Two stages are best as the first stage to about half expansion provides support for the tubeplate ligaments between all holes before the tubeplate is subject to heavier forces during the final expansion - prevents any possible distortion of the now well used tubeplates. Then the tubes will require the same two stage expansion in the smokebox but not the prosser rolling.

  • In the meantime, work has also been undertaken on the 22 new flues. As received these were covered by a tenuous protective coating which has taken some elbow grease and kero followed by steam cleaning to remove it - not the sort of stuff we need in a boiler trying to make clean steam. The task took longer than it should have with a dysfunctional steam cleaner having long moments of laying down and only providing cold water - no steam!! There could be some difficulties with the fitting of the flues into the rebored holes in the smokebox tubeplate which are now to drawing size. So are the new flues meaning there is not much clearance between the tubes and holes. But it has only just been discovered that for some reason some flues are oval by 0.040" or 1 mm - not much but enough to make them a tight squeeze across the wide diameter. The cleaned flues are currently being annealed then the ends will need the same cleaning and polishing as the tubes.
   




April and May 2011

The boiler re-tubing was progressed, however not without the usual hiccups that are encountered along the way. Trial fitting of the superheater flues proved not to be as straight forward as would be expected, when attempts to insert a flue into the fireman’s side lower row came to a halt with the flue only travelling about 2 feet into the hole and nipping up on the tube plate. Investigations found an appearance of ovality between the flue and flue hole. Removal of the flue for a closer inspection and measurements of both the flue and the flue hole revealed some ovality in the recently rebred hole and a considerable amount of oversize ovality in the flue. Added to the hole ovality was the fact that the ovality in the hole put the finished OD of the hole at its smallest diameter 5.552” as opposed to drawing size of 5.562”. The flue used for the trial fitting as it turned out, was the worst of all the flues for ovality with measurement of approximately 5.545” obviously making it an extremely tight fit with the slightly rough surface finish. Subsequently all holes were measured to determine the extent of which the boring machine had introduced ovality. The flues holes varied somewhat with several holes being within tolerances and several exceeding. Those flue holes exceeding the minimum size, required some reworking of which RCR promptly attended too, reworking all holes to the required dimensions. All flues were also inspected and reworked by means of linishing the flues to a maximum OD of 5.540” using a template to gauge the flues. The second fitting attempt proved successful with all flues being inserted along with the remaining tubes between the flues without further inserting difficulties. Flue and remaining tube expansion has been performed and completed in its initial phase with prosser rolling of the tubes as required to set the desired tube protrusion from the tube plates along with four of the top row of flues to accommodate for the uneven smoke box tube plate. All tubes and flues have been ground back to the required final lengths. Upon successful completion of boiler hydrostatic tests the firebox end and required smoke box tube ends will be seal welded, as likewise will the flues.

Fabrication and welding installation of the replacement combustion chamber plates is complete. The three separate sections were individually trimmed to size and inserted and tacked into place. The two large sections were fitted and fully welded into place prior to the installation of the boiler tubes and flues as a number of old tubes had been reworked and installed as longitudinal stays in order to ensure the fire box tube plate remained firmly anchored during the removal and replacement of plates in the combustion chamber. The remaining third section of plate has been removed and new plate installed since the tube installation. All 108 stay holes have been bored and tapped into the new plates ready for installing stays. Shaun Cassidy and Oliver Lukins spend many hours using a manufactured jig, boring and tapping holes for the precise fit of the new stays. All stays, stay cups, stay cup caps and copper sealing rings have been manufactured by Dinki Di engineering and supplied. Stay installation has begun, expecting to take approximately two days to insert and set up the new stays and replacement cups. David Groves will seal weld the stays and stay cups once installation is complete. All 108 stays require seal welding on the fire box side.

Shaun, Oliver and Ron Norell have spent two weeks working on the loco over the pit to replace a worn engine trailing truck centre pivot pin and lower bush. The worn pin and bush were indentified in the 2008 work and were given a limited life. Both pin and bush (hardened) have been installed to the trailing truck pivot. The pit work has also comprised of repairs to the rear tender coupler dampening package mounting cradle. The cradle has required some extensive pad welding and grinding to restore the worn rubbing surfaces that had subsequently worn away. This work has required a fair bit of building up and dressing back in order to restore squareness to the cradle mounting. A template has been made to provide and accurate fit for the somewhat heavy dampening package that will now be reinstalled in its mounting cradle. The rear tender draw gear will then be refitted to the tender.

   

Several hours have already been spent inspecting and cleaning up components that make up the regulator, superheater elements, element hole blanks, and other smoke box fittings in readiness for hydrostatic testing and steam testing. The regulator valve spindles and seats have been cleaned up or recut as required ready for installation. The superheater elements have been tap tested and cleaned ready for hydro testing to 1000psi prior to installation into the boiler. Upon successful completion of hydro tests there is many hours of welding required to the tube ends in the firebox and required ends in the smoke box.

The boiler re-tubing was progressed, however not without the usual hiccups that are encountered along the way. Trial fitting of the superheater flues proved not to be as straight forward as would be expected, when attempts to insert a flue into the fireman’s side lower row came to a halt with the flue only travelling about 2 feet into the hole and nipping up on the tube plate. Investigations found an appearance of ovality between the flue and flue hole. Removal of the flue for a closer inspection and measurements of both the flue and the flue hole revealed some ovality in the recently rebred hole and a considerable amount of oversize ovality in the flue. Added to the hole ovality was the fact that the ovality in the hole put the finished OD of the hole at its smallest diameter 5.552” as opposed to drawing size of 5.562”. The flue used for the trial fitting as it turned out, was the worst of all the flues for ovality with measurement of approximately 5.545” obviously making it an extremely tight fit with the slightly rough surface finish. Subsequently all holes were measured to determine the extent of which the boring machine had introduced ovality. The flues holes varied somewhat with several holes being within tolerances and several exceeding. Those flue holes exceeding the minimum size, required some reworking of which RCR promptly attended too, reworking all holes to the required dimensions. All flues were also inspected and reworked by means of linishing the flues to a maximum OD of 5.540” using a template to gauge the flues. The second fitting attempt proved successful with all flues being inserted along with the remaining tubes between the flues without further inserting difficulties. Flue and remaining tube expansion has been performed and completed in its initial phase with prosser rolling of the tubes as required to set the desired tube protrusion from the tube plates along with four of the top row of flues to accommodate for the uneven smoke box tube plate. All tubes and flues have been ground back to the required final lengths. Upon successful completion of boiler hydrostatic tests the firebox end and required smoke box tube ends will be seal welded, as likewise will the flues.

Fabrication and welding installation of the replacement combustion chamber plates is complete. The three separate sections were individually trimmed to size and inserted and tacked into place. The two large sections were fitted and fully welded into place prior to the installation of the boiler tubes and flues as a number of old tubes had been reworked and installed as longitudinal stays in order to ensure the fire box tube plate remained firmly anchored during the removal and replacement of plates in the combustion chamber. The remaining third section of plate has been removed and new plate installed since the tube installation. All 108 stay holes have been bored and tapped into the new plates ready for installing stays. Shaun Cassidy and Oliver Lukins spend many hours using a manufactured jig, boring and tapping holes for the precise fit of the new stays. All stays, stay cups, stay cup caps and copper sealing rings have been manufactured by Dinki Di engineering and supplied. Stay installation has begun, expecting to take approximately two days to insert and set up the new stays and replacement cups. David Groves will seal weld the stays and stay cups once installation is complete. All 108 stays require seal welding on the fire box side.

Shaun, Oliver and Ron Norell have spent two weeks working on the loco over the pit to replace a worn engine trailing truck centre pivot pin and lower bush. The worn pin and bush were indentified in the 2008 work and were given a limited life. Both pin and bush (hardened) have been installed to the trailing truck pivot. The pit work has also comprised of repairs to the rear tender coupler dampening package mounting cradle. The cradle has required some extensive pad welding and grinding to restore the worn rubbing surfaces that had subsequently worn away. This work has required a fair bit of building up and dressing back in order to restore squareness to the cradle mounting. A template has been made to provide and accurate fit for the somewhat heavy dampening package that will now be reinstalled in its mounting cradle. The rear tender draw gear will then be refitted to the tender.

   

Several hours have already been spent inspecting and cleaning up components that make up the regulator, superheater elements, element hole blanks, and other smoke box fittings in readiness for hydrostatic testing and steam testing. The regulator valve spindles and seats have been cleaned up or recut as required ready for installation. The superheater elements have been tap tested and cleaned ready for hydro testing to 1000psi prior to installation into the boiler. Upon successful completion of hydro tests there is many hours of welding required to the tube ends in the firebox and required ends in the smoke box.

June and July 2011

On Saturday 30th July, again another long day by many, the boiler barrel was washed out in preparation for a hot water hydro test to 250psi, being 1¼ times normal operating pressure and at a temperature of 60ºC. A number of tasks are required to set up the boiler for the hot water hydro testing. These include the addition of some external “bush” plumbing to connect the circulating pump to move water around from the rear of the boiler to the front to obtain the correct temperature mix throughout the entire boiler, along with plumbing for the hydro test pump to raise the required pressure.

After several hours of work, the first fire was lit in 621’s firebox in three years thus creating a memorable moment for the monumental task undertaken. Maintaining a small fire to warm the boiler to the required temperature over a period of around 2 hours or so gave the required boiler temperature to adequately undertake the high pressure hydro test. Upon removing the hot ashes from the fire grates, the required pressure was soon achieved with very pleasing results. No sign of any leaks from either firebox or smoke box tube plates or the renewed combustion chamber plates or stays. The only unfortunate leak came about from one of the flexible ball stays close to the renewed sections of plate on the fireman’s side near the radius of the crown sheet. With the hot hydro test being a success the boiler was drained whilst warm and dried in order to carry out the stay replacement.

   

Spare stays already manufactured by Dinki Di during the combustion chamber replacement work were of a suitable length for the required replacement however required machining down to the required diameter. Shaun and Ron have undertaken the task of removal and replacement of the affected stay.

The troublesome fireman’s side blow down valve has been overhauled by reboring the valve spindle housing and replacement of the valve spindle bush along with machining of the valve seat. The blow down valve has been reinstated along with the original blow down muffler once again enabling boiler blow downs from both sides of the boiler.

Superheater element installation has now been completed along with many of the smoke box fittings and baffles. When the con rod, bent by a errant motorist in 2008, returns from straightening by HeavyMech all rods will be refitted. A further cold water hydro of the replaced stay and superheater elements will be performed along with a number of servicing tasks in readiness for steam testing.



August 2011

Most recently all the loco’s brake cylinders habe been inspected, nearly 20 years since the last inspection, and it was found that one of the engines brake pistons has some cracking. Interestingly enough the cracking appears to have ben caused by sand inclusion during its original casting process. This was found by attempting to dig the crack out in order to stop its progression however the inclusion was soon located as the crack got deeper. Interesting how these things take so many years to come out. The crack was actually visible with the naked eye.

Work on 621 over the past weeks has gone very much to schedule. This is mostly due to the majority of tasks falling into place with little or no trouble or delay and as a result of a couple of marathon Saturdays where work went late into the evenings. Thanks to David Groves and Shaun Cassidy for their assistance in duties over and above on these days, along with the other volunteer input.

Recent tasks have seen the installation of all 108 flexible stays and three flexible stay cups as manufactured by Dinki Di Engineering. The cup threads retaining the cup caps on three cups had significant wastage in their threads requiring them to be replaced with new cups. The photos below show David applying pre-heat to the outer boiler barrel prior to welding the cups in place and inside the firebox combustion chamber seal welding the stays on the fire side.

Much preparation work had been performed leading up to Saturday July 2, wíth the boiler's first cold water hydro test to 100 psi - the first filling of the boiler since November 2008. Installation of “blanks” (fitted into the water side of the regulator header) in place of the normal superheater elements, permitted just the boiler itself to be hydro tested. The superheater elements had already been hydro tested to 1000psi. These blanks posed a problem during the cold water hydro due to a split retaining collar. This collar is used to apply pressure against the socket for sealing in the regulator header. During the 100psi test, water streamed from several places in the smoke box tube plate including the header blank. This required removal of all superheater blanks to insert the flue expander to further expand the flues to take up all leaks. It was at this time we noted the fractured collar. A number of days were spent in both the fire box and smoke box expanding tubes and flues until the boiler remained water tight and held pressure for several hours without leaks. This is certainly not the best time of the year for getting wet during these tasks.

With all flues and tubes holding pressure at 100psi and with the boiler then drained, welding of all flues and tubes in the fire box and appropriate stay tubes in the smoke box was performed as per current day standards. This task required approximately seven full days welding to complete. Once the welding was complete a further 100psi hydro test ensured any tubes upset during the welding process were “nipped up” by post welding expanding as required.



   



Steam loco 621 restoration complete!

The final step in 621's restoration was a test run to Goolwa depot and return on Sunday August 21st hauling steel car 710 and DE loco 958. The trip was a success with the boiler steaming excellently, as would be expected with an all new heating surface of tubes and flues. With the exception of one oil feed pipe to the driver’s side piston rod coming loose and the fireman’s side trailing truck axle box running rather warm all else ran like a Swiss watch. Tied in with some very crisp stack talk produced by the baker valve gear, there were smiles as far as the eye could see.

621 has subsequently hauled the regularly scheduled Southern Encounter and Highlander commencing on Sunday August 28th and will continue as train loco right through to the end of November, fire restrictions permitting.

For the record, final workshop milestones were:

  • Work on loco 621 previously went very much to schedule in July and August. The majority of the few remaining tasks were completed with little or no trouble or delay and as a result of a couple of marathon Saturdays where work went late into the evenings. We thank key players Craig Dunstan, David Groves and Shaun Cassidy for their assistance supported by other members of our volunteer mechnical services team. Installation of all 108 flexible stays and three flexible stay cups as manufactured by Dinki Di Engineering. The photo at the end of this report shows David inside the firebox combustion chamber seal welding the stays on the fire side.

  • On Saturday July 2 the first cold water boiler hydro test to 100 psi marked the first filling of the boiler since November 2008. With all flues and tubes holding pressure at 100psi and with the boiler then drained, welding of all flues and tubes in the fire box and appropriate stay tubes in the smoke box was performed as per current day standards. This task required approximately seven full days welding to complete. Once the welding was complete a further 100psi hydro test ensured any tubes upset during the welding process were “nipped up” by post welding expanding as required.

  • On Saturday 30th July, again another long day by many, the boiler barrel was washed out in preparation for a hot water hydro test to 250psi, being 1¼ times normal operating pressure and at a temperature of 60ºC. A number of tasks are required to set up the boiler for the hot water hydro testing. These include the addition of some external “bush” plumbing to connect the circulating pump to move water around from the rear of the boiler to the front to obtain the correct temperature mix throughout the entire boiler, along with plumbing for the hydro test pump to raise the required pressure.

  • In late July the first fire was lit in 621’s firebox in three years (top photo) marking a memorable moment for the monumental task undertaken and in mid August the fireman’s side conrod that was bent during the accident in 2008 and repaired by contractors HeavyMech, looking much straighter now, will be installed with the remaining rods. The boiler was then scheduled to undergo a full steam test with a test run to follow a week or so later.








CLICK HERE to return to our current loco maintenance tasks